Smoke control in a stairwell: flow rate, pressurisation and the door that must still open

This chapter details the rules for installing and balancing a stairwell pressurisation system. You will learn how to set the supply air flow rates, calibrate the relief devices to maintain the required overpressure and check the opening force of emergency doors with a dynamometer during acceptance tests.

Key takeaways

  • Stairwell overpressure prevents smoke from entering from the affected landings.
  • The opening force of emergency doors must under no circumstances exceed one hundred newtons.
  • The mechanical pressure relief damper or relief flap compensates for pressure variations.
  • The final tests measure the air velocity with the door open and the pressure with the doors closed.

Maintaining overpressure without blocking the emergency doors

Stairwell pressurisation, often referred to as a differential pressure system, meets a vital requirement: to guarantee an escape route that is passable and free of smoke in the event of a fire. According to the AEAI fire protection guidelines, this staircase is the main vertical evacuation route for occupants and the priority access route for fire service personnel. To prevent any penetration of hot, toxic gases when a landing door is opened, the supply fan forces a flow of fresh air directly into the volume of the stairwell.

The airflow challenge lies in managing two opposing physical states. When all exits are closed, the fan introduces a volume of air into a sealed enclosure, which causes a rapid rise in static pressure relative to the adjacent corridors or dwellings. If this pressure becomes excessive, the force exerted on the door leaf opposes the direction in which people are escaping. Uncontrolled overpressure pneumatically locks the leaves that open inwards into the stairwell, or blocks the exits to the outside of the building if the evacuation flow pushes against the compressed air.

Pressurisation system (pressure differential)
Mechanical safety ventilation system designed to establish a positive pressure difference between a protected space (stairwell, lobby) and the adjacent affected areas, in order to push back smoke.

The AEAI fire protection guidelines set the reference overpressure at 50 pascals with the doors closed. This value guarantees a robust airflow barrier against the thermal effects of fire. However, the force required to operate the latch and fully open the access door at the evacuation level must not exceed 100 newtons at the handle. This limit includes both the mechanical resistance of the door closer, the friction of the seals and the airflow force due to the pressure differential acting on the surface of the door leaf.

To stabilise the system between the two operating modes, the ventilation contractor installs a rapid relief device. Two main technical solutions are used: a mechanical pressure relief damper with a calibrated counterweight, or a fast motorised damper controlled by a high-resolution differential pressure sensor connected to a frequency converter on the ventilation motor. The relief device discharges the excess air to the outside as soon as the set-point threshold is reached, preventing pressure from building up when the doors slam.

Setting the flow rates and carrying out tests under evacuation conditions

The supply fan unit must be sized to meet a dual airflow criterion calculated by the design office in accordance with the AEAI fire protection guidelines. On the one hand, the fan must compensate for all the natural air leakage of the stairwell (door gaps, roof access hatches, duct penetrations) while maintaining the regulatory 50 pascals. On the other hand, it must provide a large flow rate to guarantee a minimum sweep velocity through one or more doors deliberately held open.

Airflow acceptance criteria under the AEAI guidelines
Test configurationParameter measuredNominal target valueAcceptance tolerance
All doors closedRelative pressure differential50 PaPermissible range 40 to 60 Pa
All doors closedOpening force at the latchLess than 100 NStrict maximum 100 N
Emergency door openMean air velocity through the opening1.0 to 2.0 m/sContractual minimum 0.75 m/s
Sudden door closureDamper stabilisation timeLess than 3 secondsImmediate return below 50 Pa
  1. Preparing the measuring instrumentsInstall a calibrated differential manometer with static pressure taps: a sampling tube placed in the centre of the stairwell and a reference tube placed on the floor landing, outside the discharge cone.
  2. Measurement with the doors closedStart the safety ventilation system. Record the pressure gradient at each level of the building to check that the supply is uniform along the shaft and that the value stabilises at 50 pascals.
  3. Checking the force with a dynamometerHook a mechanical or digital dynamometer perpendicular to the handle of the evacuation door. Pull slowly until the latch bolt is completely released and note the maximum force applied, which must remain below 100 newtons.
  4. Measuring the sweep velocity with the door openOpen the door of the critical landing or the final exit door designated in the safety concept. Measure the air flow velocity through the open doorway with a vane anemometer at a minimum of eight points spread across the opening.

The contractor bears in mind the duty of careful performance arising from the contract for work: art. 364 CO provides that the contractor is liable for the proper and faithful performance of the work entrusted to them. In the case of a fire safety installation, neglected balancing directly engages the contractor's technical liability during the official inspection by the cantonal fire protection authority.

Controlling the pressure gradient and managing air leakage

The differential pressurisation system of a stairwell follows a strict airflow equation. According to the AEAI fire protection guidelines, the fundamental objective is to physically prevent hot gases and toxic smoke from entering the vertical escape volume by creating a pneumatic barrier. However, blowing a large flow of air into an enclosed space increases the pressure against the walls and on the openings. If the internal pressure rises uncontrollably, the thrust exerted on the access doors prevents occupants from operating the latch to escape from the affected floors.

To reconcile smoke tightness with the evacuation of users, the ventilation installer must guarantee two distinct airflow regimes: static overpressure with the doors closed and sweep velocity at the crossing of the open door. In the closed regime, the target pressure differential between the stairwell and the adjacent rooms is usually 50 Pa (with a tolerance range of 20 Pa to 50 Pa permitted depending on the configuration). As soon as a door leaf opens, the volume of air escapes suddenly; the supply fan must then instantly deliver a sufficient compensating flow rate to produce an outgoing air velocity of at least 1.0 m/s through the free section of the opening, thus pushing back the smoke stagnating on the landing.

Operating airflow parameters according to the access configuration
Stairwell configurationAirflow criterion targetedAssociated technical deviceSafety objective
All doors closedRelative pressure of 20 to 50 PaGravity-operated pressure relief damper or frequency controlPrevent swing doors from being blocked (force below 100 N)
One landing door openMinimum air velocity of 1.0 m/sFan acceleration or closing of the relief damperCreate an opposing air flow that blocks smoke from the landing
Final exit door openMaintaining a sweep flow rateAir discharge at roof level or smoke vent damper at the top of the stairwellAvoid direct venting to the atmosphere without control of the flow

To stabilise this unstable system, two control technologies coexist on construction sites: the mechanical pressure relief damper with gravity-operated blades calibrated by counterweight, or the electronic system combining a frequency converter driving the axial fan and a piezometric differential pressure sensor. The mechanical damper responds almost instantaneously when doors slam, whereas electronic control requires very short ramp-up times (generally less than 3 seconds) so that the pressure does not fall below the regulatory thresholds or create a residual blocking overpressure.

On-site measurement protocol and acceptance in the evacuation configuration

Validating the mechanical smoke control of a stairwell is not limited to checking that the fan rotates. It requires a meticulous measurement campaign carried out on site using a calibrated differential manometer, a vane (or hot-wire) anemometer and a mechanical or digital dynamometer. In accordance with the rules of the trade under CFC 244, the contractor carries out the work under their own technical direction, within the framework of their duties of performance governed by art. 364 CO. It is up to them to prove that the installation fully meets the expected physical values before official acceptance by the cantonal fire safety services.

  1. Measuring the mechanical force on the access doorsWith the fan switched off, use the dynamometer to measure the force needed to overcome the door closer alone. Put the system into forced fire mode, with the doors closed. Attach the hook of the dynamometer to the operating lever at the regulation handle height. Pull perpendicular to the plane of the door leaf: the total force measured to release the door from the frame must under no circumstances exceed 100 N.
  2. Measuring the relative pressure gradientPlace the reference static pressure tap capillary in the adjacent circulation area (outside the pressurised zone) and connect the positive tap inside the stairwell. Record the differential at each level, in particular on the ground floor and the top level, to detect vertical disparities.
  3. Checking the velocity at the crossing in evacuation modeSimultaneously open the door of the landing assumed to be affected and the final exit door leading outside. Using the anemometer, measure the velocity of the outgoing air flow at a minimum of 8 points across the free opening of the open door leaf in order to establish the arithmetic mean velocity, which must reach the prescribed design value.

All the values recorded — total supply air flow rates in m³/h, pressure differentials per landing in pascals, opening forces in newtons and crossing velocities in metres per second — are documented in an airflow test report. This document certifies the perfect coordination between the supply flow rate and the air relief paths that are essential to guarantee the survival of the people being evacuated.

Resolving non-conformities during evacuation tests

On the construction site, commissioning a stairwell pressurisation system frequently reveals two opposing defects: either the overpressure collapses as soon as a door leaf is opened, or the evacuation door remains pressed against its frame under the airflow thrust. The AEAI fire protection guidelines set a strict framework: the stairwell must remain free of smoke through a regulated pressure gradient relative to the affected zones, while guaranteeing an opening force, measured at the lever, that never exceeds the manual force an occupant can reasonably exert, i.e. 100 N on the dynamometer.

  1. Opening force above the limit thresholdIf the dynamometer records more than 100 N on a fire door opening inwards towards the landing, the mechanical pressure relief damper or the calibrated counterweight relief damper is reacting too slowly. The balancing weights should be adjusted, or the response speed of the frequency converter control linked to the differential pressure sensor should be increased, in order to cap the overpressure below 50 Pa in less than three seconds after closing.
  2. Insufficient air velocity through the open doorWhen the anemometer records a crossing velocity below the set value of at least 1 to 2 m/s through the open door of the simulated affected level, the supply fan is not compensating for the overall leakage of the stairwell. The installer checks the tightness of the technical access hatches, of pipe sleeves not sealed with mortar and of the perimeter sealing of the glazed frames before recalibrating the set-point flow rate ranges of the supply unit.
  3. Instability and hunting of the pressure controlViolent pressure oscillations often come from a poorly positioned differential sensor, exposed to the direct flow of the supply outlets or to the turbulence of an intermediate landing. The measuring sensor must be moved to an airflow dead zone, at mid-height of the floor, connected by rigid pressure tubes without kinks, with an outdoor reference tap sheltered from the dynamic effects of wind on the façade.

Frequently asked questions

How should the opening force be measured precisely according to the AEAI requirements?

The measurement is made using a calibrated dynamometer attached perpendicular to the operating lever, at the usual point where the hand is applied. The installer operates the handle to unlock the lock, then pulls slowly and continuously until the door leaf comes away from its frame. The peak value recorded during the phase when the seal is released must not exceed 100 N in the smoke control configuration in operation.

Why does the door refuse to close completely under overpressure?

The supply air flow creates a resistant air cushion that slows the end of travel of the door leaf just before the latch bolt engages. This phenomenon occurs when the relief damper discharges the excess air accumulated in the volume too slowly. The solution is to coordinate the adjustment of the hydraulic latching speed of the door closer and to check the discharge sensitivity of the calibrated pressure relief damper.

Where should the air supply points in the stairwell be sensibly located?

For tall stairwells, a single supply at the bottom or at the top creates excessive pressure differences along the shaft. The supply must be distributed vertically through a dedicated air duct, with supply grilles spaced at least every three levels. This configuration limits thermal gradients and guarantees a uniform overpressure of between 20 and 50 Pa over the whole shaft.

How is the evacuation configuration simulated during the technical acceptance tests?

The official test requires the final exit door to the outside and at least one fire door of the affected landing to be held open at the same time. The supply fan must provide the prescribed sweep flow rate through these open openings while maintaining the regulatory overpressure on all the other landings whose accesses remain closed, without tripping the electrical installation through airflow overload of the motor unit.

Texts and standards cited

  • Directives de protection incendie AEAIRequirements applicable to pressurisation systems for smoke control and for keeping vertical escape routes passable.