Skip to content
Website
🧱 CFC 244Section 3 of 610 chapters

Air-handling unit and heat recovery: the execution reference

This section is aimed at ventilation fitters, team leaders and CFC 244 foremen responsible for positioning, assembling and adjusting air-handling units. It details the practical rules for spatial layout, the air-side connection of heat recovery units, the sizing of traps under negative pressure, filter staging and anti-vibration decoupling. The aim is to guarantee the hygienic airflows and energy efficiencies required by SIA 382/1, without hydraulic de-priming or acoustic transmission to the building structure.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

norme SIA 382/1

50 Pa

Minimum water seal added to the calculated negative pressure of the casing for the trap

norme SIA 382/1

1 m 00

Minimum free lateral clearance in front of the access doors of an air-handling unit

norme SIA 382/1

2.0 m/s

Maximum recommended face air velocity at the coils and filters

art. 41 OTConst

2 m

Fall height from which collective roof-edge protection is required

Technical scope and execution interfaces of the air-handling unit

The ventilation system installer bears full responsibility for the air-handling casing, from its unloading to the delivery of airflows at the supply terminals. On a Swiss construction site, the unit is the central node where the fresh air, exhaust air, supply air and extract air flows converge. The CFC 244 fitter's work covers the mechanical assembly of the sections, the alignment of the casings, the fitting of the filter media, the installation of insulating flexible connectors and the direct air-side connection of the thermal coils.

To preserve the works warranties and avoid disputes on the construction site, the boundaries of services between trades must be applied with absolute rigour during installation:

  • Hydraulic coils: the air-side connection, airtightness to air passage, the installation of the capillary frost protection sensor and the fitting of the damper blades fall under CFC 244. By contrast, the hot or chilled water distribution network, the three-way valves, the circulators and the connection to the threaded or flanged pipe stubs belong to the heating installer (CFC 241).
  • Condensate drainage: the supply and installation of the ball trap or trap with a calculated water seal, the hydraulic priming and the drain piping down to the air break belong to CFC 244. The sanitary drainage stack downstream of the disconnected funnel falls under the sanitary installer (CFC 250).
  • Electrical connection and control: the mechanical fitting of the differential pressure sensors, thermostats and damper actuators is the responsibility of the ventilation fitter. The supply of the power feed to the local isolator depends on the electrician (CFC 232), while the communication bus, the digital addressing and the BMS controller fall under the integrator (CFC 238).
  • Structural work and openings: the marking out of the openings in slabs or concrete walls is provided by the ventilation fitter, but the execution of core drilling and load-bearing openings remains reserved for the mason (CFC 211.1).

The employer and the supervisory staff ensure that assembly and handling operations comply with the rules of good construction practice to prevent any bodily harm, in accordance with the Swiss Criminal Code (art. 229 CP). As regards material installations and working methods in plant rooms or on roofs, the company applies the protective measures prescribed by the Ordinance on the Prevention of Accidents and Occupational Diseases (OPA).

Working method: from positioning to functional adjustment

Installing an air-handling unit requires a sequence of ordered steps. An error of anticipation regarding an overall dimension or a plinth height permanently compromises access to the filters or the draining of the condensate tray.

  1. Handling, crane lifting and seating of the machineLogistics begin with checking access routes. If the unit is installed on a flat roof, chapters K3-10 and K3-01 guide the slinging plan, compliance with the permissible loads on the slab and the provision of the lateral clearances essential for opening the doors to 90 degrees and withdrawing the filter drawers without hitting the walls of the room.
  2. Acoustic decoupling and condensate treatmentBefore any tightening of the ducts, chapters K3-07 and K3-03 deal with the structure-borne sound isolation of the casing by means of elastomer or spring mounts and sealed flexible connectors. The trap is made immediately: its water seal must absolutely offset the maximum negative pressure created by the fan, in order to prevent condensate being drawn into the air stream.
  3. Integration of the heat recovery systemThe selection and assembly of the exchanger are based on chapters K3-02, K3-05 and K3-08. Depending on whether it is a sealed plate system or a hygroscopic rotary wheel, the fitter positions the purge sector, connects the bypass dampers for summer night cooling and positions the frost protection sensors on the water heating coil.
  4. Filter hygiene and humidity conditioningChapters K3-04 and K3-09 specify the airtight installation of the ISO 16890 filter frames, the calibration of the differential clogging pressure switches and the integration of the steam humidification lances, in order to prevent any risk of bacterial growth or water saturation in the distribution ducts.
  5. Air-side performance and balancing of the operating pointsThe process concludes with chapter K3-06. The fitter checks the direction of rotation of the fan wheels, measures the current drawn on each motor phase, adjusts the frequency of the variable-speed drive and records the total airflow with the anemometric manometer in order to set the machine on the characteristic curve of the network.
Critical checkpoints when installing an air-handling unit
Item inspectedRisk of malfunctionCheck to be carried out on site
Condensate trayInternal overflow and flooding of insulationMeasure the geometric height below the tray base and fill the trap with water before testing
Supply filtersBypass of dirty air and fouling of the exchangersCheck the continuous compression of the sealing gaskets on the retaining rails
Flexible connectorsStructure-borne sound bridge and negative pressureCheck the clearance of at least 30 mm without excessive tension or twisting of the fabric
Bypass damperDrop in heat recovery efficiency in winterVisually test the mechanical tightness of the blades when fully closed at 0 %

📘 Chapters in this section 10

Air handling unit and heat recovery

Positioning the air-handling unit: maintenance clearances, door and filter replacement

Guarantee access to the internal components by observing the opening and withdrawal distances without hitting the walls.

Air handling unit and heat recovery

Rotary or plate: efficiency, moisture transfer and recirculation risk

Select the suitable exchanger by controlling pressure carry-over to eliminate any risk of odour contamination.

Air handling unit and heat recovery

Draining condensate: water seal, negative pressure and the trap that loses its prime

Calculate the water seal heights precisely to stop water overflowing inside the machine.

Air handling unit and heat recovery

Filters: class by use, measured fouling and actual replacement interval

Optimise the filtration stages to maintain hygienic quality without suffering unnecessary excess electricity consumption.

Air handling unit and heat recovery

Connecting coils: flow direction, venting and frost protection

Protect your water coils against destructive frost through a perfect counter-flow hydraulic connection.

Air handling unit and heat recovery

Setting fans: operating point, variable-frequency drive and current draw

Set the drive parameters to align the actual airflow with the network curve without overloading the motor.

Air handling unit and heat recovery

Decoupling the air handling unit: mounts, flexible connectors and structure-borne noise

Eliminate the transmission of structure-borne noise by fitting high-performance flexible connectors and anti-vibration mounts.

Air handling unit and heat recovery

Free cooling: bypass of the heat recovery unit, summer nights and limits

Make use of cool outdoor night air with a tight bypass damper to relieve the chillers.

Air handling unit and heat recovery

Humidifying without contaminating: humidifier type, hygiene and maintenance

Install a hygienic humidification lance while avoiding stagnant water deposits and the growth of legionella.

Air handling unit and heat recovery

Installing a rooftop air-handling unit: lifting, slinging and permissible load

Secure the removal and crane lifting of the casings onto the roof without exceeding the permissible load-bearing capacity.