Air-handling unit and heat recovery: the execution reference
This section is aimed at ventilation fitters, team leaders and CFC 244 foremen responsible for positioning, assembling and adjusting air-handling units. It details the practical rules for spatial layout, the air-side connection of heat recovery units, the sizing of traps under negative pressure, filter staging and anti-vibration decoupling. The aim is to guarantee the hygienic airflows and energy efficiencies required by SIA 382/1, without hydraulic de-priming or acoustic transmission to the building structure.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
50 Pa
Minimum water seal added to the calculated negative pressure of the casing for the trap
1 m 00
Minimum free lateral clearance in front of the access doors of an air-handling unit
2.0 m/s
Maximum recommended face air velocity at the coils and filters
2 m
Fall height from which collective roof-edge protection is required
Technical scope and execution interfaces of the air-handling unit
The ventilation system installer bears full responsibility for the air-handling casing, from its unloading to the delivery of airflows at the supply terminals. On a Swiss construction site, the unit is the central node where the fresh air, exhaust air, supply air and extract air flows converge. The CFC 244 fitter's work covers the mechanical assembly of the sections, the alignment of the casings, the fitting of the filter media, the installation of insulating flexible connectors and the direct air-side connection of the thermal coils.
To preserve the works warranties and avoid disputes on the construction site, the boundaries of services between trades must be applied with absolute rigour during installation:
- Hydraulic coils: the air-side connection, airtightness to air passage, the installation of the capillary frost protection sensor and the fitting of the damper blades fall under CFC 244. By contrast, the hot or chilled water distribution network, the three-way valves, the circulators and the connection to the threaded or flanged pipe stubs belong to the heating installer (CFC 241).
- Condensate drainage: the supply and installation of the ball trap or trap with a calculated water seal, the hydraulic priming and the drain piping down to the air break belong to CFC 244. The sanitary drainage stack downstream of the disconnected funnel falls under the sanitary installer (CFC 250).
- Electrical connection and control: the mechanical fitting of the differential pressure sensors, thermostats and damper actuators is the responsibility of the ventilation fitter. The supply of the power feed to the local isolator depends on the electrician (CFC 232), while the communication bus, the digital addressing and the BMS controller fall under the integrator (CFC 238).
- Structural work and openings: the marking out of the openings in slabs or concrete walls is provided by the ventilation fitter, but the execution of core drilling and load-bearing openings remains reserved for the mason (CFC 211.1).
The employer and the supervisory staff ensure that assembly and handling operations comply with the rules of good construction practice to prevent any bodily harm, in accordance with the Swiss Criminal Code (art. 229 CP). As regards material installations and working methods in plant rooms or on roofs, the company applies the protective measures prescribed by the Ordinance on the Prevention of Accidents and Occupational Diseases (OPA).
Working method: from positioning to functional adjustment
Installing an air-handling unit requires a sequence of ordered steps. An error of anticipation regarding an overall dimension or a plinth height permanently compromises access to the filters or the draining of the condensate tray.
- Handling, crane lifting and seating of the machineLogistics begin with checking access routes. If the unit is installed on a flat roof, chapters K3-10 and K3-01 guide the slinging plan, compliance with the permissible loads on the slab and the provision of the lateral clearances essential for opening the doors to 90 degrees and withdrawing the filter drawers without hitting the walls of the room.
- Acoustic decoupling and condensate treatmentBefore any tightening of the ducts, chapters K3-07 and K3-03 deal with the structure-borne sound isolation of the casing by means of elastomer or spring mounts and sealed flexible connectors. The trap is made immediately: its water seal must absolutely offset the maximum negative pressure created by the fan, in order to prevent condensate being drawn into the air stream.
- Integration of the heat recovery systemThe selection and assembly of the exchanger are based on chapters K3-02, K3-05 and K3-08. Depending on whether it is a sealed plate system or a hygroscopic rotary wheel, the fitter positions the purge sector, connects the bypass dampers for summer night cooling and positions the frost protection sensors on the water heating coil.
- Filter hygiene and humidity conditioningChapters K3-04 and K3-09 specify the airtight installation of the ISO 16890 filter frames, the calibration of the differential clogging pressure switches and the integration of the steam humidification lances, in order to prevent any risk of bacterial growth or water saturation in the distribution ducts.
- Air-side performance and balancing of the operating pointsThe process concludes with chapter K3-06. The fitter checks the direction of rotation of the fan wheels, measures the current drawn on each motor phase, adjusts the frequency of the variable-speed drive and records the total airflow with the anemometric manometer in order to set the machine on the characteristic curve of the network.
| Item inspected | Risk of malfunction | Check to be carried out on site |
|---|---|---|
| Condensate tray | Internal overflow and flooding of insulation | Measure the geometric height below the tray base and fill the trap with water before testing |
| Supply filters | Bypass of dirty air and fouling of the exchangers | Check the continuous compression of the sealing gaskets on the retaining rails |
| Flexible connectors | Structure-borne sound bridge and negative pressure | Check the clearance of at least 30 mm without excessive tension or twisting of the fabric |
| Bypass damper | Drop in heat recovery efficiency in winter | Visually test the mechanical tightness of the blades when fully closed at 0 % |
📘 Chapters in this section 10
Positioning the air-handling unit: maintenance clearances, door and filter replacement
Guarantee access to the internal components by observing the opening and withdrawal distances without hitting the walls.
Air handling unit and heat recoveryRotary or plate: efficiency, moisture transfer and recirculation risk
Select the suitable exchanger by controlling pressure carry-over to eliminate any risk of odour contamination.
Air handling unit and heat recoveryDraining condensate: water seal, negative pressure and the trap that loses its prime
Calculate the water seal heights precisely to stop water overflowing inside the machine.
Air handling unit and heat recoveryFilters: class by use, measured fouling and actual replacement interval
Optimise the filtration stages to maintain hygienic quality without suffering unnecessary excess electricity consumption.
Air handling unit and heat recoveryConnecting coils: flow direction, venting and frost protection
Protect your water coils against destructive frost through a perfect counter-flow hydraulic connection.
Air handling unit and heat recoverySetting fans: operating point, variable-frequency drive and current draw
Set the drive parameters to align the actual airflow with the network curve without overloading the motor.
Air handling unit and heat recoveryDecoupling the air handling unit: mounts, flexible connectors and structure-borne noise
Eliminate the transmission of structure-borne noise by fitting high-performance flexible connectors and anti-vibration mounts.
Air handling unit and heat recoveryFree cooling: bypass of the heat recovery unit, summer nights and limits
Make use of cool outdoor night air with a tight bypass damper to relieve the chillers.
Air handling unit and heat recoveryHumidifying without contaminating: humidifier type, hygiene and maintenance
Install a hygienic humidification lance while avoiding stagnant water deposits and the growth of legionella.
Air handling unit and heat recoveryInstalling a rooftop air-handling unit: lifting, slinging and permissible load
Secure the removal and crane lifting of the casings onto the roof without exceeding the permissible load-bearing capacity.