Key takeaways
- The systematic survey of existing openings and of the height under slab governs any ductwork route.
- The remaining false-ceiling height often requires flat ducts to be run in a dry screed.
- Decentralised per-apartment solutions eliminate slab penetrations and limit fire-stopped crossings.
- Any compromise on nominal airflow rates must be recorded in writing in the tender.
The survey of openings and the height under slab dictate the distribution
Forcing the principle diagram of a new building onto an existing one is the fitter's classic mistake. In refurbishment, no route is fixed before a destructive physical probe or a full scan of the ceiling voids. The ventilation installer checks the actual alignment of the old natural-draught flues, the slab thickness, the position of beam downstands and the unexpected presence of sanitary pipes in service shafts believed to be free. Any undetected obstacle forces a multiplication of offsets, increasing the linear pressure loss and the noise level at the terminals.
The available ceiling height determines the distribution principle. In traditional rental housing from the 1960s or 1970s, the raw height under slab is often limited to 2.50 m. Creating a general false ceiling of 25 cm in corridors and dry rooms downgrades the habitable area under municipal building regulations. The installer therefore prefers to run the supply and extract air ducts through circulation areas or wet rooms (bathroom, WC, storeroom), crossing the lightweight partitions to the bedrooms via flat-jet supply plenums.
| Configuration | Plenum height required | Advantages in an existing building | Main constraints |
|---|---|---|---|
| Centralised collective network | 200 to 300 mm in access corridor | A single unit on the roof or in the basement | Heavy fire-stopped penetrations between floors |
| Individual monobloc in false ceiling | 180 to 220 mm locally | Short networks, no slab crossings | Difficult access for changing filters |
| Room-by-room units | 0 mm (wall-mounted) | No secondary air distribution network | Multiple core drillings in the façade |
The option of decentralised machines per apartment becomes essential as soon as vertical routes are non-existent or full. The unit is placed in a technical cupboard, above the toilets or on a blind wall of a laundry room. This method spares the installer from working in the common areas, eliminates the installation of fire dampers between floors and allows fine adjustment of airflows according to the occupancy of each dwelling, while keeping the air intake and exhaust ducts on the outer façade.
The three integration compromises and the contractual fixing of airflow rates
Fitting a balanced-flow network into a constrained volume requires technical trade-offs. The installer cannot guarantee at the same time a high standardised air change rate, an air velocity below 2.5 m/s and the complete disappearance of the ducts without eating into the living space. Three compromises must be analysed on the construction site before ordering the equipment:
- Reducing the cross-section offset by multiplying the ducts: Replacing a 160 mm circular duct with three semi-rigid ducts of 75 mm or 90 mm allows a beam downstand to be crossed without choking the air, but increases the linear length and the volume of the distribution boxes.
- Adjusting the air distribution pattern: Giving up supplying air exactly opposite the door in small bedrooms. The supply is delivered as a jet along the corridor via wall grilles with a Coanda effect, avoiding crossing the room with visible boxes.
- Revising the maximum airflow: In some old dwellings where false ceilings are ruled out, the peak flow is set at the strict hygiene threshold rather than at night-time over-ventilation comfort, in order to limit the cross-sections.
Height under slab and compactness: the shift to decentralised per-apartment solutions
In residential buildings predating the 1990s, the clear height under slab frequently ranges between 2.40 m and 2.50 m. Creating a general false ceiling to distribute supply and extract air from a collective unit on the roof or in the basement destroys the spatial compliance of the living rooms. As soon as the survey of existing routes reveals the absence of free vertical technical risers or the presence of main beams with downstands every three metres, the layout of a centralised network becomes a technical dead end. The installer then shifts the distribution to flat semi-rigid ducts housed exclusively in the circulation corridor and the service rooms.
This space constraint often leads to abandoning the collective riser in favour of decentralised per-dwelling solutions. An individual monobloc unit with a counter-flow or enthalpy exchanger is installed directly above an entrance hall cupboard, in a bathroom false ceiling or above a storeroom door. Outdoor air intake and exhaust go through the façade of the dwelling concerned by means of specific horizontal core drillings. This approach eliminates the installation of fire dampers between floors and removes space conflicts with sanitary drainage.
| Site criterion | Centralised collective network | Decentralised monobloc per dwelling |
|---|---|---|
| Impact on clear heights | False ceiling needed in common areas and bulky drops | Lowering confined to the entrance lobby and wet rooms (140 mm max) |
| Structural crossings | Vertical floor core drillings with fire dampers required | Two façade core drillings per apartment, no floor penetration |
| Airflow balancing | Complex: depends on pressure losses of the lower floors | Independent: direct adjustment on the unit according to the actual size of the unit |
| Maintenance access | Grouped on the roof or in the basement, outside the dwellings | Filters and traps to be inspected directly in the tenant's home |
For the terminal ducts, rectangular networks in large-section galvanised steel sheet give way to modular high-density polyethylene manifolds. Oval ducts of 132 × 52 mm section or circular ducts of 75 mm outside diameter line up side by side without any crossing. Supply terminals are placed above bedroom doors, which limits the duct length to a few metres in the distribution hall and avoids cutting into the ceilings of the main rooms.
Contractual recording of airflow concessions and noise level in the tender
Adapting the route to the built configuration forces acceptance of higher flow velocities in reduced ducts or, conversely, throttling airflows to preserve acoustic comfort. The company must never hide these trade-offs behind a purely theoretical sizing. Where the available cross-section requires an air velocity above 3 m/s in a distribution plenum, the risk of whistling at the terminals increases significantly if the secondary silencers cannot find the geometric space to be fitted.
- The guaranteed volumetric flow per room at cruising rate (m³/h) and the timed peak flow for the sanitary rooms, calculated according to the actual pressure losses of the constrained network.
- The accepted concession on the passing velocity and the selection of wide-slot supply terminals to limit regenerated noise at the outlet.
- The target residual sound pressure level in the bedrooms, specifying that the absence of baffle silencers requires the maximum fan speed to be throttled.
- The exclusion of façade penetration work and lintel reinforcement, which remain the responsibility of the site management and the mason.
This contractual transparency protects the installer at commissioning. At the time of the airflow check with an anemometer or Pitot tube on the measuring sleeves, the values recorded must match the airflow sheet included in the validated quote. If the tender fixes a compromise of 20 m³/h per bedroom instead of the generous flows of new-build in order to fit within a 120 mm downstand, the client has signed for exactly that performance. The balancing and acceptance report records these measurements without any possible dispute over hygiene or acoustic emergence.
Handling unforeseen blockages and deciding on the actual route
In heavy renovation, removing the linings regularly reveals constraints that were invisible during the survey of existing routes: flat steel bars under the slab, diverted sanitary pipes or disused but load-bearing flues. As soon as the residual space rules out the calculated duct cross-section, the team leader suspends the installation of the section concerned. Continuing the installation by crushing a circular duct or pinching a bend causes massive singular pressure losses, an immediate acoustic drift at the terminals and a complete imbalance of the supply and extract networks.
- Dimensional finding and stop of the layoutMeasure the net residual clearance between the underside of the obstacle and the finished level of the planned false ceiling. If the available height falls below the critical value defined in the execution drawings, document the conflict with a dimensioned photographic record.
- Formal notice to the client's representativeNotify the blockage to the site management in writing. Under art. 365 CO, if a circumstance jeopardises the proper or timely execution of the work, the contractor informs the client, failing which he bears the consequences.
- Deciding between rerouting and decentralisationExamine, in coordination with the designer, the applicable variants: local transformation of the circular duct into a flat semi-rigid duct of equivalent cross-section, offset through a technical corridor, or switching the room concerned to a decentralised per-apartment solution if the façade penetration proves feasible.
If the client refuses the creation of a plasterboard downstand in order to preserve the clear height of the living rooms, a reduction in airflow becomes unavoidable. This adjustment is never made covertly on the monobloc's speed controller. Revising the supply air volumes requires a written addendum. This document states the rooms affected, the new values in cubic metres per hour, the foreseeable increase in regenerated noise at the grilles and the impact on the overall air change rate.
Frequently asked questions
What should be done if an unforeseen beam downstand blocks the main duct?
The layout must be stopped and the remaining height measured. Two options are open to the fitter: replace the circular duct with two equivalent flat ducts paired in parallel to pass the obstacle below the false-ceiling level, or request a horizontal core drilling from the civil engineer. If the penetration is rejected by the engineering office, the route must be diverted through a secondary offset, with written confirmation from the site management.
Why record an airflow compromise in the tender rather than in the minutes?
Recording airflow concessions in the tender legally fixes the airflow limits accepted by the client before the contractual commitment. Entering this tolerance in a simple site minute comes too late, often after the monobloc has been purchased. The tender states in black and white that the available height under slab restricts the diameter of the ducts, which relieves the contractor of responsibility for failing to meet the standard theoretical air change values.
How to switch from a centralised installation to individual decentralised units?
This change occurs when the collective vertical risers passing through the slabs prove impossible to core without weakening the load-bearing structure. The installer then proposes installing a compact decentralised unit in a cupboard or false ceiling of each dwelling. This solution eliminates the common vertical ducts and the associated fire dampers, but requires the direct drilling of two airtight wall penetrations in the façade per dwelling for air intake and exhaust.
What acoustic impact does the use of flat ducts in a tight false ceiling have?
Using flat ducts to get around the lack of height increases the air flow velocity and the turbulence at the connections. The linear pressure loss increases, forcing the fan to run faster to maintain the airflow. To prevent the noise level from exceeding the admissible criteria in the bedrooms, absorption silencers must systematically be added upstream of the distribution boxes and the air velocity must be limited.
Texts and standards cited
- CO art. 365material and land: the contractor is responsible for the proper quality of the material he supplies; if the material supplied by the client or the land designated by him is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3).