Key takeaways
- Differential measurement precisely isolates the pressure losses of the components and of the duct layout.
- A flush-mounted static tapping avoids the conversion error caused by velocity energy.
- Excessive static pressure combined with low airflow reveals an air network that is too narrow.
- An abnormal pressure drop across a unit casing indicates clogging or a closed damper.
Positioning the pressure tappings and measuring the static component in the duct
On a balanced-ventilation (supply and extract) installation, finding that a setpoint airflow is not reached at the diffuser does not allow you to blame the fan motor without physical evidence. The fan delivers a total pressure that splits into dynamic pressure, representing the flow velocity, and static pressure, which acts perpendicular to the duct walls to overcome friction and fittings. Methodical checking starts with inserting a static pressure probe or a Pitot tube connected to a calibrated differential manometer. According to the balancing recommendations of standard SIA 382/1, the accuracy of airflow readings depends directly on the quality of the flow at the sampling point.
- Static pressure in the duct (pst)
- Force per unit area exerted by the air perpendicular to the duct wall, independent of the direction and velocity of the flow. It represents the potential available to overcome the air resistances of the network.
- Selecting the straight measuring sectionDrill the duct on a straight section located at least five hydraulic diameters downstream of any layout disturbance (bend, tee, reduction, damper) and two hydraulic diameters upstream of the next component, to ensure stabilised air streamlines.
- Drilling and deburring the wallMake a clean hole with a diameter suited to the air tapping socket, generally 8 to 10 mm. Carefully deburr the inside of the galvanised sheet: a metal burr pointing into the flow creates a vortex that distorts the reading by several tens of pascals.
- Positioning the measuring tipInsert a dedicated static tip or the side tapping of a Pitot tube. The sensing axis must be strictly perpendicular to the flow. If you use a combined tube, point the nose into the airflow to measure total pressure on the positive port and use the side openings for static pressure.
- Connecting to the differential manometerConnect the silicone tube from the measuring tapping to the positive port of the manometer for a duct under positive pressure (supply after the fan) or to the negative port if the duct is under negative pressure (extract before the fan), the other port remaining open to the reference ambient pressure.
Interpreting the actual operating point against the fan curve
The diagnosis is based on superimposing the measured actual point (overall extracted or supplied airflow in m³/h and available external static pressure in pascals) on the air performance curve supplied by the manufacturer of the air-handling unit. At a stabilised rotational speed (motor frequency set to 50 Hz or 10 V setpoint on an electronically commutated motor), a fan can only operate at one precise point on its characteristic curve. Comparing the measured value with the HVAC engineer's forecast reveals the exact nature of the airflow blockage.
| Manometer reading | Overall airflow | Position on the curve | Probable physical cause |
|---|---|---|---|
| Static pressure clearly higher than calculated | Much lower than setpoint | Shifted to the left (high-load zone) | Undersized network, closed fire damper or blocked damper |
| Static pressure lower than forecast | Lower than or equal to setpoint | Shifted to the right or below the nominal curve | Insufficient rotational speed, slack belt, fouled impeller |
| Abnormal localised pressure loss across a unit casing | Gradually decreasing | Movement along the curve to the left | Clogged filters (construction site dust) or blocked coil |
| Very low static pressure with high internal airflow | Low at the terminals | Shifted to the far right of the curve | Disconnected duct, open branch or missing access hatch |
When the static pressure measured at the unit outlet clearly exceeds the theoretical design pressure loss while the airflow struggles to build up, the signature is unmistakable: the network has excessive resistance. This resistance may come from a balancing damper left locked in the closed position, a fire damper that has not been reset, or a flow section that is too narrow because of a spatial coordination conflict in the false ceiling. If the network is structurally undersized, trying to increase the drive frequency beyond the nominal point leads to prohibitive electrical overconsumption and noise nuisance that does not comply with Swiss comfort requirements.
Airflow signature: telling an undersized network from a clogged component
When the fan runs at its nominal speed but the terminals do not deliver the setpoint airflow, the pressure measured in the network is the only indisputable evidence. A rotational speed at its limit combined with insufficient airflow systematically reveals an overall pressure loss higher than that assumed in the design. The technical challenge is then to locate this resistance: is it a locally obstructed element or duct sections that are generally too narrow?
To decide, the measurement of total pressure and static pressure must be broken down by segment. A fouled filter, a balancing damper mistakenly left closed or a coil clogged by construction site dust creates a sudden, concentrated pressure drop. Conversely, an undersized network spreads its linear and local pressure loss over the whole length of the layout. The Pitot tube combined with the differential manometer makes it possible to record the pressure gradient on either side of each component, then along the straight sections.
| Anomaly observed | Static pressure measurement | Change on the fan curve | Physical cause on the installation |
|---|---|---|---|
| Clogged filter or fouled coil | Very high local differential pressure jump across the component | Point shifted to the left, high total pressure at the unit | Build-up of construction site dust, saturated media, crushed fins |
| Undersized network (ducts too narrow) | Continuous and abnormally high pressure gradient per metre of duct | Network parabola too steep, crossing the curve at low airflow | Installation error, premature reduction in cross-section, bends with too short a radius |
| Blocked balancing damper or damper | High static overpressure immediately upstream, relative negative pressure downstream | High point on the curve, airflow collapsed on the branch concerned | Blade mechanically jammed, actuator incorrectly indexed, faulty manual control |
| Major leak in the duct network | Very low static pressure throughout the network relative to the unit airflow | Point shifted to the right on the curve (high fan airflow) | Disconnected sealing joints, open access hatch, disconnected duct |
On the manufacturer's airflow curve, the actual point indicates the intersection between the fan characteristic and the network characteristic. If the network is too narrow, the network resistance curve takes the form of a parabola much steeper than that of the design: the fan generates a high static pressure at its terminals, but the air is restricted by the excessive wall friction and the multiplication of local turbulence.
Qualifying the defect and compliance with standard SIA 382/1
Standard SIA 382/1 sets strict requirements for the electrical power absorbed by fans for air transport. When a distribution network has insufficient cross-sections, forcing the fan with a frequency drive to reach the specified airflow makes the specific power consumption soar. The system then exceeds the energy tolerance limits permitted for ventilation and air-conditioning installations.
Proof of undersizing is established by measuring the mean velocity through the duct using a multi-point measuring grid. If the actual velocity clearly exceeds the design values set by the technical concept while the overall airflow remains below nominal, the geometric constriction is proven. The ventilation installer records these readings in the commissioning protocol: total static pressure measurement of the unit, floor static pressures, local pressure losses of the heat exchangers and electrical consumption at the motor terminals.
If the layout on the construction site was reduced to make way for other trades without prior approval, the contractor relies on these measurements to record the facts. Art. 365 CO para. 3 provides that if a circumstance jeopardises the proper or timely execution of the work, the contractor must inform the client immediately, failing which the contractor bears the consequences. The pressure measurement report, appended to the commissioning record, documents the technical impossibility of reaching the airflows without restructuring the ducts or formally recalibrating the project requirements.
Arbitration and handling of critical pressure deviations
When the static pressure measurement confirms an operating point outside tolerance, the ventilation fitter must neither arbitrarily change the damper stops nor push the drive beyond the rated current of the electric motor. If the overall airflow remains clearly below the project requirements while the total pressure at the unit terminals already exceeds the pressure losses calculated by the engineers, the origin of the blockage lies in the external air network and not in the air-handling machine.
- Isolating the pressure loss by componentUse the differential manometer to record the differential static pressure across each component: filter housing, heat recovery coil, regulating dampers and sound attenuators. An abnormal pressure drop across a new filter indicates clogging by construction site dust or an unsuitable model.
- Checking the operating point on the curveMeasure the rotational speed with an optical tachometer and record the total pressure delivered by the fan. Plot these values on the manufacturer's characteristic curve: if the actual point lies on the manufacturer's curve at reduced airflow and high pressure, the machine is suffering from excessive duct resistance.
- Recording and notifying in accordance with standard SIA 118Draw up a joint measurement record detailing the static pressures recorded on each section. If bends that are too sharp, abrupt asymmetric reductions or crushed ducts create unforeseen local resistances, send written reservations to the site management in accordance with the rules of standard SIA 118.
Methodical differential pressure measurement provides the technical evidence needed to qualify the defect objectively and to distinguish the fitter's responsibility from the designer's.
Frequently asked questions
How can you make sure the static pressure tapping is not measuring dynamic pressure?
To measure static pressure exclusively in a duct, the sampling hole must be perfectly flush with the inner wall, with no residual metal burr pointing into the airflow. If you use a Pitot tube or a static pressure probe, orient the rod at 90 degrees to the air velocity vector. Any inclination towards the flow picks up a fraction of the dynamic pressure and distorts the reading.
What does a high static pressure measured just before a new filter housing reveal?
A very high static pressure measured upstream of a filtration stage, together with an excessive differential pressure between its two faces, reveals a clear airflow anomaly. On a clean filter, this result betrays either the installation of a filter cell of a filtration class that is too restrictive compared with the engineering assumptions, or premature clogging by fine plaster or concrete dust generated on the construction site before commissioning.
How can you tell a closed damper from an undersized duct by measurement?
The pressure signature allows an unambiguous decision. A balancing damper left closed or a tripped fire damper causes a sudden pressure break: the static pressure is very high directly upstream of the component and collapses to a near-zero value just downstream. Conversely, continuous undersizing produces a steady pressure gradient and high linear pressure losses along the whole layout.
What are the permitted airflow tolerances according to standard SIA 382/1?
Standard SIA 382/1 defines the acceptance criteria for air installations. For the overall airflow measured at the unit, the permissible deviation from the setpoint is usually within a tolerance range of plus or minus ten per cent. At individual terminal outlets, a maximum deviation of fifteen per cent is commonly tolerated during balancing, provided the overall balance is maintained.
Texts and standards cited
- SIA 382/1Ventilation and air-conditioning installations - General principles and performance
- SIA 118General conditions for the execution of construction works