Key takeaways
- The height of the water seal directly offsets the maximum negative pressure prevailing in the cooling section.
- An insufficient water seal blocks gravity drainage, floods the casing and releases stale odours.
- The trap requires systematic initial filling and a mechanical valve against evaporation in dry periods.
- The drain must always be connected with an air break and removable plugs for complete cleaning.
Calculating the geometric height of the trap under the fan's negative pressure
In an air handling unit, the cooling coil and the condensate tray are commonly located upstream of the supply fan impeller. This zone operates under strong negative pressure relative to the plant room. If the drain connection is left open to the air or fitted with an ordinary plumbing trap, the internal negative pressure draws ambient air through the pipework. This continuous air draw prevents the water from draining by gravity: the condensate accumulates at the bottom of the tray, overflows onto the internal walls of the unit, soaks the acoustic insulation and saturates the filter stages located downstream.
To allow the water to drain despite the suction of the unit, the trap must have a specific geometry defined by two critical dimensions: the effective water seal height H2 and the inlet height difference H1. The maximum permissible negative pressure in service, expressed in pascals (Pa), is converted into millimetres of water column (mmWC). The water seal H2 corresponds to the height of the outlet leg measured between the low point of the bend and the overflow water line. It must be equal to the maximum negative pressure divided by ten, plus a safety margin of 25 to 50 mmWC to absorb variations in pressure drop caused by the progressive clogging of the filters.
| Static negative pressure (Pa) | Theoretical equivalent (mmWC) | Water seal H2 (mm) | Inlet clearance H1 (mm) |
|---|---|---|---|
| 250 Pa | 25 mm | 50 mm | 75 mm |
| 500 Pa | 50 mm | 75 mm | 125 mm |
| 750 Pa | 75 mm | 100 mm | 175 mm |
| 1000 Pa | 100 mm | 125 mm | 225 mm |
The inlet height H1, measured between the bottom of the drain tray and the outlet water line of the trap, must absolutely absorb the water column drawn upwards when the fan starts. If H1 is less than the negative pressure converted into millimetres plus half of H2, the water is immediately drawn back into the unit, losing the trap's prime before gravity drainage even begins. When ordering the support frame or building the concrete plinth, the ventilation installer must check that the free height under the tray outlet allows the total trap height H1 + H2 to be accommodated.
Implementing slopes, air break and maintenance against loss of prime
The diameter of the drain must never be reduced relative to the outlet sleeve of the condensate tray, the minimum size generally being set at DN 32 or DN 40. Undersized pipework promotes rapid clogging by residual dust, pollen and the bacterial biofilm that develops naturally on the fins of the cooling coil. The connection between the casing and the trap must have a continuous downward slope of at least 2 % to ensure complete emptying of the tray and prevent any residual water from standing between two operating cycles.
The ventilation contractor's discharge pipework must always stop above a funnel or trap device belonging to the sanitary installations (CFC 250). A rigid, sealed connection plugged directly into the building's wastewater system is prohibited. An open-air gap of at least 20 mm (air break) is mandatory between the end of the condensate pipe and the upper edge of the receiving funnel. This physical discontinuity protects the air handling unit against contamination by backflow of soiled water and prevents decomposition gases from entering the air circuit if the technical trap dries out accidentally.
- Initial filling and visual checkBefore the very first start-up of the fans, or after a prolonged shutdown out of season, fill the trap with clean water from a can through the access connection until it overflows clearly into the funnel.
- Fitting ball or membrane trapsDuring a summer shutdown or in a dry climate prolonging the coil's inactivity, evaporation dries out the trap within a few weeks. Fit a trap designed specifically for ventilation, equipped with a floating ball or an elastomer valve that blocks the air passage as soon as the water level drops.
- Fitting cleaning plugsInspection tees fitted with threaded plugs, or quick-release fittings, must be installed at the trap bends to allow mechanical rodding and removal of sludge without cutting the pipes.
Connection diameter, commissioning and prevention of dry loss of prime
Direct connection to the drain outlet of the condensate tray requires rigorous sizing of the collector to avoid any laminar choking or accidental backing-up. A tray under strong negative pressure retains water as long as the balancing water column is not established. If the diameter of the drain pipe is too narrow, surface tension and hydraulic pressure losses slow the gravity flow, causing the condensate to overflow inside the air handling casing as soon as the fans start.
The drain diameter must never be reduced relative to the threaded sleeve or welded flange supplied by the casing manufacturer. Even on small compact ventilation units delivering less than 2 000 m³/h, the route of the drain pipe must maintain an internal cross-section of at least 32 mm, increased to 40 mm or even 50 mm as soon as the dehumidification coil exceeds 1.5 m² of face area. Smaller cross-sections cause hydraulic plugs due to the agglomeration of fine dust carried along with the condensation water droplets.
| Estimated condensate flow | Minimum internal diameter | Minimum drainage slope | Connection to the network |
|---|---|---|---|
| Up to 15 l/h | DN 32 (1 1/4") | 20 mm/m (2 %) | Funnel with free air gap |
| From 15 to 60 l/h | DN 40 (1 1/2") | 20 mm/m (2 %) | Funnel with free air gap |
| More than 60 l/h | DN 50 (2") | 15 mm/m (1.5 %) | Funnel with air break |
Initial filling is an essential step before the fan wheels are turned for the first time. Starting up a unit connected to an empty trap without water immediately causes outside air or drain gases to be drawn through the water seal. The internal negative pressure then physically prevents the newly condensed water from descending into the leg of the trap. The water accumulates in the tray, stagnates around the coil fins and ends up being sprayed into the supply duct by the air velocity.
Inspection devices, rodding and sanitary maintenance protocols
The trap of an air handling unit is a receptacle conducive to the growth of biological deposits, mould and metal oxides. The absence of regular cleaning causes partial clogging that alters the effective water seal and promotes the transmission of unpleasant odours or contaminants to occupied areas. The mechanical design of the drain must absolutely include the possibility of quick dismantling without heavy tools.
- Installation of removable union fittings immediately upstream and downstream of the trap loop.
- Systematic installation of a tee with a threaded cleaning plug on the downpipe to allow rodding without complete removal.
- Preferential use of transparent traps made of rigid plastic, allowing direct visual checking of the water level and the presence of sludge.
- Maintaining a lateral clearance of at least 400 mm around the trap body for the passage of cleaning brushes and the unscrewing of the bottom caps.
In terms of contract and safety, the installer ensures the proper condition of the technical elements placed under his responsibility as a contractor. Under art. 364 CO, the builder of ventilation installations is liable for the care taken in carrying out the work and applies the specific rules of the trade for air flows. He coordinates the exact outlet elevation with the sanitary installer to ensure that the axis of the air break is indeed above the overflow level of the receiving floor trap.
At installation acceptance, the visual inspection and hydraulic test are carried out with the unit at nominal operation. The technician pours a calibrated volume of water into the drip tray under the maximum design negative pressure. The flow must start immediately towards the funnel without any audible air backflow, without a bubble emulsion at the bottom of the bowl, and without residual overflow at the casing of the unit.
Diagnosis and corrective measures in the event of trap malfunction
On an air handling unit under negative pressure, a drainage failure shows up through two main symptoms: stale odours pushed back into the supply network, or overflow of the condensate tray inside the casing. Faced with a flooded tray while the fan is running at full speed, the first reflex on the construction site is to switch off the ventilation. If the accumulated water drains spontaneously as soon as the air flow stops, the diagnosis is unequivocal: the internal negative pressure outweighs the water column and blocks gravity drainage owing to insufficient water seal height.
To remedy this problem without raising the whole machine, checking the height available under the bottom of the tray is essential. If the concrete plinth is too low to accommodate the calculated loop — that is, the maximum negative pressure in millimetres of water column plus fifty millimetres of safety — the installer must take action on the structure. The contractor then applies art. 365 CO by informing the client that the plinth supplied compromises the proper execution of the ventilation installation. Pending raising of the plinth or core drilling, fitting a ball trap with an anti-return membrane is a temporary technical solution to avoid dry loss of prime without requiring a large height difference.
| Observed fault | Probable physical cause | Corrective measure on site |
|---|---|---|
| Overflow when running, drains when stopped | Water seal lower than the casing's negative pressure | Raise the AHU base or fit a ball trap |
| Sewer odour in the supply network | Trap that has lost its prime through evaporation, or direct connection | Fill the trap and restore the air gap downstream |
| Permanent standing water in the tray | Reverse slope or obstruction by bacterial biofilm | Correct the slope to at least 2 % and rod the collector |
In the event of fouling by sludge or algae, removing the cleaning plugs allows immediate mechanical cleaning with a brush. The installer checks the tightness of the removable fittings and carries out systematic water filling before any restart of the supply unit.
Frequently asked questions
How do you size the water seal height on a cooling coil under negative pressure?
The formula requires a minimum water seal in millimetres equal to the maximum negative pressure of the unit expressed in millimetres of water column, plus a safety margin of 50 mm. For a negative pressure of 600 Pa, i.e. about 60 mmWC, the height between the low point of the trap and the overflow must reach at least 110 mm. A smaller dimension blocks the flow and retains the water in the casing.
Why connect the trap to an open funnel rather than directly to the pipe?
A direct connection to a wastewater stack exposes the unit to the suction of sewer gases as soon as the trap dries out. The air break through a funnel open to the air creates an air gap of at least 20 mm. It prevents any contamination of the building's hygienic air and protects the ventilation installation against fluid backflow if the downstream sanitary network becomes blocked.
How do you avoid the trap losing its prime during winter periods without condensation?
In winter or mid-season, the cooling coil does not dehumidify and the water in the trap evaporates under the effect of the ambient air. Using a mechanical trap with a floating ball maintains airtightness even when dry. Failing this equipment, the operator must schedule a manual water injection or add a few millilitres of neutral biodegradable oil, which forms a protective film limiting evaporation of the liquid reserve.
What are the slope and diameter requirements for the condensate collector?
The outlet pipe must respect the nominal diameter of the tray sleeve, without reduction, generally 32 or 40 mm diameter in rigid synthetic material. The horizontal pipe requires a regular slope towards the drain of at least 1.5 to 2 %. This inclination ensures self-cleansing velocity, prevents deposits of organic matter and eliminates any standing water conducive to the growth of legionella.
Texts and standards cited
- CO art. 365materials and ground: the contractor is liable for the good quality of the materials he supplies; if the materials supplied by the client or the ground designated by him are found to be defective, or if any other circumstance compromises the proper or timely execution of the work, he must inform the client immediately, failing which he bears the consequences (para. 3)
