Key takeaways
- Steam humidification guarantees maximum hygiene with no risk of droplet carry-over into the ducts.
- Washers and trickle humidifiers require automatic draining cycles and regular water treatment.
- The slope of the drip tray must ensure complete drainage without any stagnant retention zone.
- The maintenance log proves the traceability of the mandatory cleaning and disinfection operations prescribed by the manufacturers.
Technology choice: steam or trickle humidification in light of hygiene requirements
Injecting water into an air handling unit is a critical point for indoor air quality. A poorly designed or neglected humidification section turns the treatment casing into a biological reactor, spreading legionella, bacteria and fungal spores throughout all the rooms served. To meet the requirements of SIA 382/1, the ventilation fitter must master the physical principles and operating constraints specific to each family of equipment.
Humidification systems must be designed and operated in such a way as to prevent any proliferation and any emission of micro-organisms into the treated air flow.
Norme SIA 382/1
Steam humidification is the inherently safest solution from a bacteriological point of view. The steam produced by immersed electrodes, electric heating elements or a heat exchanger fed by the heating network is sterile when released into the air stream. The fluid is injected in gaseous form through perforated distribution manifolds fitted with precise nozzles. The absence of liquid droplets eliminates the risk of contaminated aerosols, provided that the absorption distance is strictly respected to avoid condensation on the casing walls or on downstream components.
Conversely, trickle or evaporative humidification on a contact medium uses liquid water circulating at air temperature. The air passes through a honeycomb pack that is continuously wetted. This technology has a favourable energy balance owing to the associated adiabatic cooling, but it introduces a mass of liquid water in direct contact with airborne impurities. If the water is not constantly renewed and drained, the wet pack traps organic dust and promotes rapid microbial growth.
| Criterion | Steam humidifier | Adiabatic trickle humidifier |
|---|---|---|
| Humidity carrier | Dry steam at atmospheric pressure | Demineralised water trickling over a medium |
| Direct microbiological risk | None at emission (natural thermal sterilisation) | High in case of stagnation or absence of biocontrol |
| Evaporation length required | Absorption distance of 0.5 to 1.5 metres depending on the manifold | Medium thickness (0.3 to 0.6 metres) with droplet separator |
| Sensitive components to inspect | Injection manifolds, condensate traps, cylinders | Collection tray, contact pack, circulation pump |
| Water drainage constraint | Manifold condensate and cylinder blow-down | Automatic complete draining and scheduled periodic flushing |
Preventing biological stagnation: tray design, draining and traceability
Standing water is the absolute enemy of air-handling hygiene. In a trickle system, the water that has not evaporated falls back into a lower tray made of stainless steel or polypropylene before being recycled or discharged. As soon as the humidity demand or the ventilation stops, this water must disappear. SIA 382/1 prescribes design provisions that prevent any retention of lukewarm water in the casings, the optimum zone for bacterial growth between 20 °C and 45 °C.
The collection tray must have a continuous multidirectional slope towards the drain point of at least 2 %. No residual puddle must remain at the bottom after the drain valve has been opened. The unit's control system must include an automatic sequence that completely drains the tray and the pipework after a predefined period of inactivity, generally between 12 and 24 hours, followed by a forced drying cycle by ventilation without spraying.
- Connecting the trap under negative pressureFit a ball trap or a swan-neck trap whose water seal is calculated according to the maximum static pressure of the fan, with venting to prevent loss of the seal.
- Checking the droplet separatorCheck the alignment and cleanliness of the separator profiles placed at the medium outlet to prevent any carry-over of liquid droplets at air velocities above 2.5 m/s.
- Disinfection and chemical flushingPeriodically treat the trickle cassettes with the disinfectants approved by the manufacturer, using no agents that corrode stainless steel and no volatile toxic substances.
- Recording in the unit's logDocument the date, the water conductivity measurements, the replacement of cylinders or media and the intervention signatures in the installation's technical register.
Decontamination protocols and purge automation
The water introduced into the supply air flow must never become a culture medium. In an air handling unit, any contact between the distributed air and lukewarm water directly exposes occupants to aerosols laden with micro-organisms, fungal spores or endotoxins. While steam injection systems largely avoid this danger thanks to the boiling temperature, adiabatic trickle or spray humidifiers require strict physical and logical barriers to prevent biofilm formation.
To stop bacterial proliferation in washers and trickle media, the ventilation installation must include a programmed complete drying. SIA 382/1 imposes provisions to prevent droplet carry-over and the deterioration of indoor air quality. The shutdown sequence of a trickle humidifier does not simply mean stopping the recirculation pump: it commands the opening of a complete drain valve at the low point, followed by a period of dry-air sweeping over the honeycomb panel before the supply fan is switched off.
| Humidification technology | Flushing or purge trigger | Management of prolonged shutdown | Mechanical or chemical action required |
|---|---|---|---|
| Steam by electrodes or heating elements | Automatic purge controlled by the conductivity of the water in the cylinder | Complete draining of the cylinder after 24 hours of continuous inactivity | Cylinder replacement or periodic acid descaling of the tank |
| Trickle over a once-through medium (lost water) | Automatic draining of the manifold after each interruption of demand | Closing the upstream solenoid valve and gravity draining of the pipework | Annual disinfection of the distributor and preventive replacement of the cassettes |
| Recirculating trickle (with tray) | Continuous partial renewal or forced purge every 2 to 4 hours | Complete draining of the tray with forced drying by the ventilation air flow | Manual cleaning of the tray, brushing of the bottom and approved disinfection of the circuit |
| High-pressure atomisation (nozzles) | Automatic flushing of the injection lines before each atomisation cycle | Depressurisation and complete purge of the stainless steel manifolds | Fouling check of the nozzles and disinfection of the upstream header |
Upstream water treatment directly determines the hygiene of the casing. Softened water prevents scaling but does not eliminate bacteria; worse, ion-exchange resins can become microbial sources if they are not regularly disinfected. Reverse-osmosis filtration, supplemented if necessary by an ultraviolet disinfection reactor, reduces mineralisation and bacterial load without resorting to volatile biocides that could be carried into the occupied areas.
Hygienic maintenance, air checks and operating log
The operator and the installer share responsibility for flawless follow-up from the commissioning of the installation. Art. 364 CO provides that the contractor is liable for the proper and faithful execution of the work. For air handling units, delivering a ventilation unit without clear preventive maintenance procedures exposes the building manager and the installer to serious claims if a pulmonary contamination occurs in the rooms served.
- Visual and olfactory inspection of the casingCheck that there is no standing water on the unit floor, check the surface condition of the droplet separators and look for any start of mould on the sound-insulation walls immediately downstream of the wet section.
- Checking condensate drainageTest the water fill of the ball trap, check that no polluted air is pushed back from the discharge pipes and measure the continuous slope of the tray bottom directed towards the drain opening.
- Microbiological water and contact samplingTake samples using agar contact slides on the wet surfaces and take a water sample from the tray or the manifolds to count the total aerobic flora and test for legionella.
- Recording operations in the maintenance logEnter every medium replacement, descaling, water analysis or network flushing in the technical log of the air handling unit, available for hygiene audits.
SIA 382/1 sets out the hygiene criteria applicable to ventilation and air-conditioning installations. The supply air must not contain any concentration of particles or germs higher than that of the filtered outdoor reference air. Although the steam humidifier offers high intrinsic safety through its operating temperature, it nevertheless requires monitoring of the overheating sensors and maintenance of the distribution to prevent any premature condensation in the air ducts.
Crisis protocol and restoration of a contaminated section
A fault on an air humidifier — visual detection of a slimy film of biofilm, presence of stale water following the blocking of a purge solenoid valve, or a smell of damp soil blown into the ducts — requires a methodical response. As soon as the hygiene criteria prescribed by SIA 382/1 are breached, the air handling unit becomes an active spreader of pathogenic micro-organisms, legionella and endotoxins throughout all the ventilated rooms.
- Hydraulic isolation and drying of the sectionIsolate the raw or softened water supply to the appliance. Keep the fan motor running to evaporate the residual liquid film on the contact packs, the lances and the droplet separators.
- Complete draining and manual scouringForce open the trap and the tank-bottom drain valve. Remove the accumulated sludge, scale and organic deposits using a soft brush, then rinse abundantly towards the drain.
- Replacing porous consumablesOn a trickle humidifier, always discard the evaporation cassettes impregnated with algae or bacteria; their honeycomb structure can never be disinfected right through. On steam injection, descale the cylinder and unblock the manifolds.
- Check sampling and traceabilityCarry out tank water analyses to check the total germ count after flushing. Carefully record the date, the parts replaced and the analytical results in the installation's maintenance log.
Recommissioning must not be improvised. To protect the safety and health of persons, the employer takes the protective provisions and measures that meet the recognised rules of technology under art. 3 OPA. Any unit whose water loop shows recurrent bacterial contamination must remain locked out of humidification until the source has been definitively eliminated and the hygiene protocol has been validated in writing.
Frequently asked questions
Why is steam humidification preferred in Swiss hospitals?
Steam injection produces germ-free humidification, because raising the water temperature above 100 °C sterilises the vaporised flow. Unlike trickle humidifiers or cold-water atomisers, steam generates no liquid aerosol capable of carrying live bacteria such as legionella. This process eliminates the reservoir of stagnant lukewarm water in the casing, ensuring strict compliance with the hygiene criteria imposed by SIA 382/1 in sensitive medical environments.
What should you do if the tray of a trickle humidifier does not empty at shutdown?
Persistent standing water when not operating is a major non-conformity that promotes bacterial growth. Without delay, cut the water make-up, check the drainage slope of the tray and unblock the condensate trap. The automatic drain solenoid valve must be tested: if it remains stuck in the closed position because of scale or an electrical fault, replace its mechanism. Clean and disinfect the tank before humidification is resumed.
How often should an air humidifier be checked and drained in Switzerland?
According to the hygiene rules of SIA 382/1, automatic draining must take place at every shutdown of the unit and at least every 24 hours during periods of inactivity. Visual inspection of the trays, filters and droplet separators is carried out monthly during the heating season. A complete cleaning, descaling and replacement of the evaporation cassettes are required at least once a year during pre-season maintenance.
Can honeycomb cassettes be reused after high-pressure cleaning?
No, cleaning with a high-pressure washer is prohibited on evaporative cassettes. The pressure tears the honeycomb structure made of cellulose or mineral fibre, which alters the airflow profile and promotes carry-over of water droplets into the ducts. In addition, bacteria embedded in the thickness of the material are not destroyed by a surface jet. Any element that is clogged, scaled or colonised by a biofilm must be replaced with a new original component.
Texts and standards cited
- SIA 382/1Ventilation and air-conditioning installations - General principles and performance
- OPA art. 3Protective measures and installations: the employer takes the protective provisions and measures that meet the requirements of the ordinance, the other applicable occupational safety provisions and the recognised rules of safety technology and occupational medicine