Skip to content
Website
🧱 CFC 244Commissioning, measurement and air flow balancingChapter 6 of 10 in the section

Handing over the installation: show the filter, the trap and the circuit breaker

At the end of commissioning, the ventilation fitter passes the keys to operation on to the caretaker or technical manager. You will be able to demonstrate the three essential physical operations, display the laminated summary sheet against the air-handling unit and record this practical training in the joint handover record to prevent early breakdowns.

Key takeaways

  • Showing how the filters are removed and checking the direction of fitting guarantees the nominal airflow.
  • Filling the condensate trap prevents foul air being drawn in and water overflowing.
  • Locating the local switch makes cleaning safe and avoids false power-supply alarms.
  • The laminated sheet displayed in the plant room and the signed record seal the handover.

Passing on the three operating actions in front of the packaged unit

A ventilation installation accepted as compliant from the airflow point of view can suffer serious failures within the first months if the operating staff do not know the basic operation. On-site instruction does not mean reading a general fifty-page manufacturer's manual, but carrying out together three precise physical actions in front of the running machine.

  1. Replacing the filters and direction of fittingOpen the access doors to the filter housings in front of the operator. Slide the frame out of the guides, point to the arrow printed on the filter medium showing the direction of airflow, and show the compression of the sealing gasket. A cell fitted the wrong way round or poorly pressed home lets fine dust pass directly onto the heat exchange coils and distorts the readings of the differential pressure switch.
  2. Priming and filling the condensate trapDemonstrate filling the trap connected to the unit's drip tray with water. Under negative pressure from the extract or return fan, an empty water seal is drawn inwards: the condensation water is no longer drained, overflows into the insulation of the packaged unit and causes odours in the ducts. Fill the trap from a can of clean water to confirm gravity drainage.
  3. Isolation and local electrical resetPoint out the lockable local switch within easy reach on the housing. Show the procedure for switching off the power before any panel is opened, to prevent entrapment by the fan wheels or contact with the motorised dampers. Explain the safety reset and the difference between a clean local cut-off and a fault reported by the control system.
Visual checks and actions passed on to the operator
ComponentAction demonstratedRisk if omittedRecommended frequency
Filter cellsRemoval, checking the direction of flow, checking for cloggingExcessive pressure drop, motor overconsumption, insufficient airflowQuarterly check, six-monthly replacement
Unit trapManual filling with clean water, checking the ball valveDrawing in of exhaust air, internal flooding of the treatment housingMonthly check and before each cold season
Maintenance switchTurning to the off position, lock-out with padlockInjury from unexpected start-up during filter replacementEach time an inspection panel is worked on

Recording the handover of the installation and displaying the summary sheet

A verbal explanation does not protect the installer against later operating disputes. Once the demonstration has been carried out, the fitter must put these instructions into a visible working document and have the transfer of basic skills certified in the acceptance of the work documents.

The one-page operating sheet must be laminated or placed in a waterproof pocket fixed directly to the casing of the unit or to the wall next to the control panel. It summarises the critical data without burying the caretaker in engineering details:

  • The exact dimensions, efficiency classes and commercial references of the fresh-air and extract-air filters.
  • The single-line diagram of the installation showing the airflow, the location of the drain tray and the water height required in the trap.
  • The exact location of the emergency isolation devices and of the lockable maintenance switch.
  • The procedure to follow in the event of a frost alarm or an airflow fault, before any call to the breakdown service.
  • The emergency contact details of the ventilation company and the end date of the warranty on the works.

The handover document is signed in two original copies by the chief fitter and by the person appointed to manage the building. It expressly mentions the handover of the contractual spare filter sets, the review of the alarms and the confirmation that the operator himself removed and refitted a filter frame under the installer's supervision. This protocol closes the installation work and defines the responsibility of the ventilation installer with regard to routine maintenance defects.

Practical handover protocol: filters, water seal and local isolation

Instructing the operator does not mean handing him the technical file on the doorstep. On the construction site, the ventilation fitter has the caretaker, the property manager or the building's technical manager carry out each action in front of the packaged unit. This direct handover ensures that the person knows how to open the access panels without forcing the toggle latches, recognise the condition of a component and react before an alarm brings the whole installation to a complete stop.

  1. Replacing the filter cells on siteOpen the access door to the filter housing after switching off the ventilation. Release the slides or spring frames holding the cassettes or bag filters. Show the direction of airflow marked by the arrow on the metal frame. Slide the clogged medium into a refuse sack that is closed immediately to prevent dust spreading in the plant room. Position the new medium, lock the clamping system to guarantee the perimeter seal of the cell gasket, then read the value on the dial differential pressure gauge.
  2. Priming and checking the water seal of the trapLocate the ball trap or dip trap connected to the condensate collection tray, situated under the plate heat exchanger or the cooling coil. Unscrew the top plug or filling funnel. Pour in clean water from a watering can until it visibly overflows to the free outlet. Explain to the operator the internal negative pressure generated by the extract fan: without a sufficient water column, foul air draws the water out of the tray or the fumes from the drainage network instead of the condensate being drained.
  3. Identifying the local isolator and the circuit breakerDistinguish between the lockable maintenance switch located next to the fan motor and the assigned protective circuit breaker in the local electrical cabinet. Turn the switch to the zero position, check that the wheel stops completely, then reset. Show the exact location of the thermal-magnetic circuit breaker dedicated to the unit and explain that a nuisance trip signals a mechanical or electrical fault requiring a qualified technician, not repeated resetting.
Major incidents avoided through direct instruction of the operator
Component checkedFrequent oversightDirect consequenceCorrective action passed on
Filtration stage (fresh air)Filter fitted the wrong way round or gasket crushedRestricted airflow, bypass of dusty air, clogging of the coilCheck the airflow arrow and compress the sealing gasket
Condensate tray trapTrap de-primed by spring evaporationWater overflowing into the housing, sewer odours drawn into the ductsFill the trap with water before each switch between heating and cooling mode
Maintenance switchEmergency stop mistaken for a control stopClosing damper jammed, drive put into safe modeUse the control switch and reserve the isolator for maintenance

Permanent technical display and joint formalisation

To make these verbal explanations lasting, a laminated A4 summary sheet must be mechanically fixed or glued in a tamper-proof way directly to the access door of the packaged unit, at eye level. This single-page document serves as a permanent visual reference for maintenance staff or third-party companies working during the life of the building.

  • Standardised references and exact dimensions of the filters for fresh air and return air (class ePM1 or ePM10, thickness, metal frame).
  • Schematic diagram of the packaged unit showing the location of the sensors, the mixing dampers and the condensate trap.
  • Frequency of basic operations: quarterly visual check, six-monthly re-priming of the trap, annual replacement of the filter media.
  • Emergency numbers of the electrical installer, the packaged unit manufacturer and the ventilation company's breakdown service.
  • Emergency electrical isolation procedure and step-by-step restart procedure.

The handover session ends with the joint signature of a technical instruction record. This document explicitly lists the operations carried out jointly, the handover of the stock of spare filters provided for in the contract and the presence of the instruction sheet displayed on the machine. Under art. 370 CO, the joint check and taking over of the installation mark the transfer of custody of the work and release the installer from damage resulting from later maintenance failures.

  • Name and qualification of the person trained on behalf of the client.
  • Date and duration of the familiarisation session in the plant room.
  • Confirmation of successful operation of the isolator and replacement of a filter in front of the installer.
  • Handover of the access keys to the packaged unit panels and confirmation that the operating diagram is present.

Handling disputes over taking over and operating shortcomings

The refusal of the client or his representative to countersign the technical instruction record is a critical situation when the works are closed out. This refusal does not automatically suspend the transfer of custody of the installation if the unit is put into operational service for the needs of the building. In the event of formal opposition or absence of the designated person at the appointment, the ventilation fitter records the precise condition of the machine in a complete photographic report: new filters in place with the slides closed, transparent traps filled with clean water and the isolator padlocked in the off position as a safety measure.

Notification is made by registered letter addressed to the site management, recalling the provisions of the SIA 118 standard on acceptance of the work and the making available of the equipment. This letter includes a copy of the instruction sheet displayed in the plant room, the dated reading of the hour meters and a precise warning of the risks incurred without supervision: failure of the trap's water film under negative pressure, damage to belts or motors through premature clogging of the filter housings, and imbalance of the duct networks.

  1. Joint recordingPhotograph the laminated instruction sheet in place against the access panel of the packaged unit, the liquid levels in the traps and the calibrated differential pressure gauges of the filters.
  2. Formal placing in custodySend the unsigned commissioning report the same day, with express mention of the deadline for taking over routine maintenance.
  3. Protective isolationIf the plant room remains accessible to unauthorised third parties with no designated operator, lock out the main isolator with a padlock to relieve the installer of responsibility.

Frequently asked questions

What should be done if the condensate trap de-primes as soon as the fan starts?

This problem indicates an insufficient seal height in relation to the internal negative pressure of the housing. Check the static pressure with a differential pressure gauge, recalculate the minimum water seal required and add a vertical riser to the downpipe. Then fill the trap completely through the upper inspection plug before restarting the motor.

Can the operator vacuum the clogged filters instead of replacing them?

No. Mechanical cleaning by vacuuming destroys the micrometric structure of the fibres and opens preferential paths that let fine particles pass directly to the heat exchange coil. Pleated or bag filters are single-use consumables. Any clogging detected visually or signalled by the differential pressure threshold being exceeded requires complete replacement of the filter media.

Who is responsible for clogged filters between commissioning and acceptance?

As long as the transfer of custody formalised by the acceptance record has not taken place, the installation remains under the supervision of the contractor or the site management according to the terms of the works contract. If the unit runs to heat or ventilate the construction site before final handover, a specific sacrificial set of filters must be invoiced and then replaced before acceptance.

Where should the one-page summary sheet be placed if the room is damp?

The document must be printed on a laminated medium resistant to splashing and glued or riveted directly to the access door of the air-handling unit, next to the operating handles. It must never be hung by a simple wire from sanitary pipework or left lying flat on top of the ventilation ducts.

Texts and standards cited

  • norme SIA 118General conditions for the execution of construction work, acceptance of the work and transfer of risks
  • norme SIA 382/1Ventilation and air-conditioning installations, general principles and technical requirements

In the same section