Skip to content
Website
🧱 CFC 244Duct network and airtightnessChapter 3 of 10 in the section

Hanging the network: support spacing, deflection and vibration noise

This chapter gives you the sizing and installation rules for air-duct hangers. You will be able to determine the maximum spacing according to duct geometry, control the permissible deflection, acoustically isolate the network to eliminate resonance at start-up, and select the anchors suited to the nature of each load-bearing slab.

Key takeaways

  • Too wide a hanger spacing causes destructive vibration resonance when the fan starts up.
  • The maximum spacing generally ranges from two metres for small diameters to three metres for rigid networks.
  • The deflection of a duct must not impair the airflow or create condensation pockets.
  • Interposing elastomers between rod, rail and duct ensures the acoustic attenuation of structure-borne noise.

Defining the hanger spacing and controlling mechanical deflection

Hanging an air-duct network meets a dual requirement: carrying the static loads of the duct while absorbing the dynamic stresses generated by the airflow. When an air-handling unit is started up, the rise in pressure creates an aeraulic shock wave. If the interval between two clamps is too large, the duct starts to vibrate by resonance, which damages the tightness of the connections and spreads a dull rumble throughout the building structure.

Recommended maximum hanger intervals according to network geometry
Duct typeCharacteristic dimensionMaximum spacingHanger type
Circular spiralDiameter less than or equal to 250 mm3.00 mSingle clamp with threaded rod
Circular spiralDiameter 280 mm to 630 mm2.50 mReinforced clamp with threaded rod
Circular spiralDiameter greater than 630 mm2.00 mSection cradle or double clamp
RectangularLongest side less than 800 mm2.50 mC-section cross-member under the duct
RectangularLongest side from 800 mm to 1600 mm2.00 mHeavy cross-member and double side rods
RectangularLongest side greater than 1600 mm1.50 mPerimeter reinforcing frame with bracket
Permissible deflection of a duct
Maximum vertical deformation tolerated between two consecutive support points under the effect of the duct's own weight, its insulation if any, and internal pressures. In installation practice, this deflection must not exceed one three-hundredth of the spacing span (L/300) in order to avoid any misalignment of the joints, any risk of visible sagging and any water retention during maintenance operations.

Decoupling the supports and matching the anchoring to the slab type

The vibrations of a motor-fan unit travel along the metal walls as structure-borne noise. According to art. 22 OLT 3, noise and vibration must be avoided or combated by construction measures, measures on operating installations and isolation of the sources. Systematically breaking the rigid contact between the duct sheet metal and the structural work is the installer's first means of action.

  • Circular clamps fitted with an integrated lining of vulcanised EPDM elastomer resistant to thermal ageing.
  • Self-adhesive acoustic decoupling strips interposed between the steel cross-members and the underside of the rectangular duct.
  • Anti-vibration mounts or elastic bushes inserted at the top of the threaded rods at the point of contact with the hanger sections.
  • Sealed flexible connectors installed at the supply and return of the unit to cut the vibration wave at the mechanical source.
  1. Identify the load-bearing supportDistinguish a reinforced concrete solid slab, a prestressed hollow-core element or a trapezoidal steel deck. The drilling technique and the choice of anchor depend directly on it.
  2. Drill without damaging the structureOn solid concrete, carry out rotary mechanical drilling at the exact diameter of the anchor. In a hollow-core slab, locate the hollow cell and absolutely avoid perforating the underside of the ribs containing the prestressing cables.
  3. Fit the approved fixingUse threaded concrete screws or galvanised steel expansion anchors for a solid slab. Fit spring toggle anchors for hollow-core slabs. On steel framework with steel decking, fit beam clamps or specific hangers for trapezoidal sheet fixed by through-bolting.
  4. Adjust the levelling and tighten the lock nutAdjust the elevation of the network using a laser level. Lock each hanger nut with a tightened lock nut to prevent any loosening under the micro-pulsations generated by the passage of air.

Maximum hanger spacing and control of dynamic deflection

When an air-handling unit is switched on, the rise in static pressure and the setting in motion of the air stream apply a sudden dynamic stress to the duct walls. If the support spacing is too large, the duct sags excessively under its own weight and starts to oscillate under the effect of the initial aeraulic turbulence. This flapping phenomenon, often reinforced by the drumming effect on the long sides of rectangular ducts, generates a sharp metallic bang that travels through the hangers to the building structure. To stabilise the run, the spacing between two successive hanging points must be calculated by taking into account not only the static load of the duct and its insulation if any, but also the pull-out and deflection forces caused by transient flow conditions.

The permissible deflection of a horizontal duct corresponds to the visible sagging of the bottom generatrix or of the joint section between two hanging cradles. This sagging must never exceed one three-hundredth of the distance between two hangers, otherwise the drainage slopes for any condensate are altered and points of mechanical fatigue are created at the clips or cross frames. On circular spiral-seam ducts, the intrinsic stiffness of the tube allows a maximum spacing of up to three metres for small diameters. For rectangular ducts whose long side exceeds eight hundred millimetres, however, the support spacing must be reduced to between one metre fifty and two metres in order to prevent any deformation of the underside under the thrust of the air.

Maximum hanger spacing and deflection criteria according to duct geometry
Cross-section typeDimension rangeMaximum spacingPermissible deflection tolerated
Circular spiralDiameter less than or equal to 400 mm3.00 m1/300 of the span (maximum 10 mm)
Circular spiralDiameter between 450 and 1000 mm2.50 m1/300 of the span (maximum 8 mm)
Rectangular metalLong side less than or equal to 800 mm2.00 m1/350 of the span (maximum 6 mm)
Rectangular metalLong side greater than 800 mm1.50 m1/400 of the span (maximum 4 mm)

Acoustic decoupling and fixing methods according to slab type

Acoustic decoupling of the supports is the only effective safeguard against the transmission of structure-borne vibrations emitted by the fan and by damper turbulence. Art. 22 OLT 3 provides that noise and vibration must be avoided or combated, in particular by construction measures and isolation of the sources. In ventilation installations, each support cross-member, circular clamp or fixing bracket must be separated from the threaded rod by anti-vibration mounts made of elastomer of suitable hardness. For rectangular ducts hung from trapezoidal rails, a strip of cellular rubber or an EPDM damping profile is interposed over the full contact width under the duct to eliminate any direct steel-on-steel friction.

The mechanical sizing of the support does not guarantee stability if the anchor point in the structural work is unsuited to the substrate. Pull-out resistance depends on the receiving material and its behaviour under dynamic load.

  • Reinforced concrete solid slab: fixing is carried out with concrete screws certified for cracked concrete or with metal drop-in expansion anchors. Drilling with a hammer drill requires careful cleaning of the hole by blowing out, to guarantee the rated holding capacity under repeated loading.
  • Prestressed hollow-core slab: anchoring is restricted to the hollow cavities of the slab by means of spring toggle anchors or expansion sleeves specific to thin walls. Any drilling of the longitudinal ribs containing the prestressing strands remains prohibited, in order to preserve the structural integrity of the load-bearing element.
  • Composite floor with composite steel deck: hanging is done using hanging clamps for trapezoidal profiles fixed to the ribs, or articulated clamps fitted with locking screws. Reinforcing shims or load-spreading profiles are provided where large-size ducts risk locally deforming the galvanised sheet.

Correcting vibration faults and bringing hangers into compliance

When an air-duct network is commissioned, a surging phenomenon or a bang at unit start-up often reveals undersized supports. If the hanger spacing exceeds the recommended spans, the sheet metal goes into resonance under the effect of static pressure variations. Likewise, direct contact between a threaded rod and the slab or the edge of a cross-member creates an acoustic bridge that transmits mechanical vibrations to the building structure. In accordance with art. 22 OLT 3, noise and vibration must be avoided or combated by construction measures and isolation of the sources.

  1. Locate the origin of the vibration faultFirst inspect the flexible connector on the packaged unit to check for the absence of excessive tension or forced alignment. Then measure the deflection of the duct with a rotary laser; any deformation exceeding one three-hundredth of the span requires immediate rework of the run. Visually check each clamp and mounting rail to detect complete crushing of the insulating gaskets or omitted resilient washers under the hanger nuts.
  2. Add supplementary hangersFit intermediate hangers on the unstable sections to reduce the effective spacing to under two metres for rectangular ducts and three metres for circular spiral ducts. Use self-tapping concrete screws or metal anchors certified for cracked concrete, respecting the prescribed anchorage depth. For prestressed hollow-core slabs, use only toggle anchors or sleeves suited to thin walls, outside the zones of prestressing reinforcement.
  3. Break the structure-borne transmissionLoosen the rigid clamps and interpose EPDM rubber damping profiles between the duct and the metal cradle. If the threaded rods transmit the hum of the motors, install spring boxes or elastomer-mount hangers at the top, sized according to the actual load per support point. Check that the threaded rod never comes into metal-to-metal contact with the flange of the omega section or the fixing angle.

Frequently asked questions

How do you correct a rectangular duct that sags between two hangers?

When the deflection of a duct exceeds one three-hundredth of the spacing or causes water retention during cleaning, insert an intermediate trapeze support at the middle of the span. On large widths above eight hundred millimetres, the bottom sheet may sag under its own weight: then fix transverse stiffening angles riveted on the outside or insert tubular spacers inside to stabilise the panel without changing the overall hanger spacing.

Why does a neoprene or EPDM lining get completely crushed under a clamp?

Total crushing of the rubber profile comes from excessive tightening of the assembly screws or from an undersized lining in relation to the weight per metre of the network. The material compressed solid loses its flexibility and conducts the vibration waves directly into the threaded rod. To correct the defect, loosen the clamp until the nominal thickness of the elastomer is restored, then lock the nut with a lock nut without squeezing the insulating strip under the sheet metal.

Which anchors should be fitted in a prestressed hollow-core concrete slab?

In prestressed hollow-core slabs, drilling in the zones of steel strands is strictly prohibited. Anchoring is carried out only in the hollow cell using specific toggle anchors or short metal expansion sleeves designed for hollow-core walls at least thirty millimetres thick. Each hole must be drilled with a depth stop to avoid going through the upper flange or cutting into the prestressing reinforcement of the structural work.

How do you tell an aeraulic noise from transmission through the supports?

An aeraulic noise is characterised by a whistle or rush of air that varies directly with the flow velocity and clearly diminishes at the diffusers. Noise transmitted through the supports, on the other hand, appears as a low-frequency hum or a dull pulsation audible in the walls and concrete slabs. The diagnosis is confirmed by placing a hand on the threaded rod: a marked tactile vibration shows the absence of acoustic decoupling.

Texts and standards cited

  • OLT 3 art. 22noise and vibration: they must be avoided or combated (construction measures, measures on operating installations, isolation of the sources, work organisation).

In the same section