🧱 CFC 244Commissioning, measurement and air flow balancingChapter 10 of 10 in the section

Restarting after summer: dry trap, clogged filter and bypass left open

As soon as temperatures first drop in September, restarting air handling units generates a flood of avoidable emergency calls. Sewer odours, lack of fresh air and excess consumption almost always stem from three basic mechanical oversights. This chapter details a twenty-minute inspection method to diagnose the condensate tray, clean up the filtration, reposition the heat recovery unit and validate the nominal airflows.

Key takeaways

  • Re-priming the condensate trap with clean water neutralises the negative pressure and eliminates odours coming back up.
  • Systematically replacing filters saturated with summer pollen restores the air pressures and protects the heat exchanger.
  • Checking the bypass actuator ensures the air is forced through the heat recovery unit.
  • An airflow check with a differential manometer confirms the balance between fresh air and extract air flows.

Checking the condensate tray, the filter media and the bypass damper

At the start of autumn, air handling units undergo a sudden change in operating mode. During the summer weeks, the heating coils remained inactive and the airflows passed through exchangers often set to passive night cooling or to full bypass. When the building calls for heat input again, restarting without a methodical check immediately produces major malfunctions noticed by the occupants. Twenty minutes are enough to deal with the three critical components before switching to winter mode.

The first critical point is the condensate trap of the unit's collection tray. During the hot season, the heat in the plant rooms and the absence of condensation on the coils dried out the water seal. In casings under negative pressure relative to the plant room, the failure of this hydraulic seal causes permanent suction of stale air or drain gases. The residual water is no longer discharged: it is held in suspension by the fan's suction velocity, overflows into the casing, soaks the acoustic insulation and spreads foul odours throughout the supply network.

Water seal of the trap under negative pressure
Minimum water height maintained in the drainage loop, calculated to offset the maximum negative pressure created by the extract or supply fan so that outside air is not drawn into the casing.

The second trap comes from the filter media. Summer concentrates large loads of mineral dust, insects and fine pollen that clog the fibrous structure. This clogging causes a severe increase in pressure drop, reducing the overall airflow and causing excess electricity consumption on speed-modulated fans. It is common for the excessive negative pressure to deform the galvanised sheet-metal retaining frames or tear a flexible bag filter, letting pollutants pass directly onto the fins of the heat exchanger.

The third check concerns the bypass damper of the plate energy recovery unit or thermal wheel. Left wide open to take advantage of air cooling without heat exchange in July and August, this mechanical damper often refuses to close because of a seized linkage, a broken shaft or a detached 0-10 V actuator. The incoming fresh air then completely bypasses the exchange zone: the warm extract air is discharged at roof level without transferring its heat, which abnormally overloads the upstream heating equipment and cools the zones served.

Applying the intervention procedure and measuring airflows in twenty minutes

  1. Re-priming the drainOpen the access door of the locked-out fan casing. Remove the upper inspection plug of the plastic or transparent trap. Pour in at least two litres of clean water until a smooth flow to the drain pipe is observed, then close the plug tightly with its seal.
  2. Replacing and seating the filtration stagesRemove the clogged filter cassettes or bags. Vacuum the plant deposits accumulated on the rain grille and at the bottom of the intake chamber. Install the new set of filters, carefully checking the flow direction shown by the arrows on the frames, then lock the clamping cams.
  3. Forced operation and alignment of the bypass damperManually disengage the mechanical drive of the bypass actuator. Check that the blades close completely and that there is no gap at the lip seals. Re-engage the motor to make sure the control signal brings the exchange dampers back to full opening and closes the bypass channel.
  4. Reading the reference air pressuresClose all the airtight access panels. Restore the power supply to the unit. Measure the differential pressure across the new filtration and across the exchanger using a portable digital manometer connected to the external pressure taps.
Target values and checkpoints during the seasonal restart
ComponentTypical faultCorrective actionPermitted tolerance
Condensate trapEmpty water seal, suction noisesFilling with water and checking tightnessWater height greater than the 50 mmCE negative pressure
Fresh air filterDense dust, pressure drop doubledReplacement with a clean compliant mediumPressure difference per manufacturer data (+/- 10 %)
Bypass damperBlades partly open in recovery modeCleaning the linkage and resetting the shaft100 % visually tight mechanical closure
AirflowInsufficient velocity in the ductsMeasurement with a Pitot tube or measuring crossMaximum deviation of +/- 10 % from the execution file

The technician applies the professional rules governing his contract under the Code of Obligations (CO), ensuring careful and diligent execution of the airflow settings. When the dynamic pressure readings confirm that the supply and extract air volumes match the initial commissioning protocol, the intervention is recorded on the maintenance sheet displayed on the machine casing.

Airflow interactions and diagnosis of combined faults

At the autumn restart, the faults found on a balanced-ventilation installation rarely appear in isolation. The combined action of a filter medium clogged by summer pollen, a mechanical bypass damper set off its setpoint and a broken water seal creates an immediate imbalance across the whole air network. The excessive pressure drop on the fresh air changes the operating point of the electronically commutated fan. This increase in negative pressure in the suction casing raises the suction effort on the drain outlet of the condensate tray, which prevents any gravity drainage if the water seal height of the ball trap or loop trap has not been restored manually with a sufficient volume of water.

When the bypass damper of the plate recovery unit remains set at one hundred per cent in summer mode because of a mechanically seized linkage or an actuator fault, the incoming fresh air no longer exchanges any heat with the extract air. The supply air then enters the ducts at its raw temperature. As soon as the terminal heating coil compensates for this unexpected heat deficit without preheating on the exchanger, the energy bill climbs sharply and the supply sensors trigger erratic control sequences. At the same time, a loaded filter medium lowers the available pressure, throttling the flows at the terminal outlets geometrically furthest from the plant room.

For the installing technician, visual inspection is only a starting point. Using an electronic differential manometer connected to the original piezometric pressure taps makes it possible to check whether the static pressure difference across the exchanger corroborates the actual angular position of the bypass damper. If the actuator shows complete closure on its digital control but the pressure measurement shows almost no resistance, the aluminium blades have remained open on the bypass channel, short-circuiting the heat recovery block.

Measurement protocol, airflow recalibration and traceability

A twenty-minute intervention achieves its purpose only if each physical check results in a recorded and logged value. Replacing or blowing out the coarse and fine filters instantly changes the network's resistance curve. Before leaving the unit, the tradesperson carries out a series of readings with a Pitot tube or a damped vane anemometer directly in the straight supply and extract duct sections, in accordance with the recognised rules of air-handling technology applied to buildings.

Airflow requalification grid for the seasonal start-of-autumn visit
Component checkedTypical mechanical faultAirflow effect observedCorrective action required
Condensate trapWater seal evaporated by heatParasitic air intake and odour backflowFilling with clean water and checking the ball valve
Fresh air intake filterSurface saturation by plant debrisDrop in fresh airflow and excess motor consumptionReplacing the filter frame and calibrating the pressure switch
Exchanger bypass0-10 V actuator stuck in the open positionNo heat transfer to the supply airManual operation, shaft greasing and travel reset
Balancing dampersButterfly loosening under the effect of vibrationsDrift in discharge velocities at the diffusersDynamic pressure measurement and mechanical locking

Under art. 364 CO, the contractor carries out the work in person or under his personal direction. In technical terms, this requirement of rigour obliges the installer to certify that the restarted installation meets the original sanitary and thermal requirements set out in the execution file. The volumetric flow readings, expressed in cubic metres per hour, must match the engineer's setpoint flows, within the permissible tolerance of plus or minus ten per cent accepted on commercial or residential air distribution networks.

  1. Refilling and purging the trapInject at least two litres of clean water into the trap's water seal using a service can. Check the free descent of the sealing ball or the stabilised level in the loop before closing the airtight access panel of the casing.
  2. Kinematic check of the bypass damperTemporarily cut the automatic control signal to force the damper to close completely by mechanical means. Visually confirm that the lip seals bear tightly against the sheet-metal stops of the plate exchanger.
  3. Reading the differential pressure across the new filtersMeasure the initial pressure drop using a manometer connected to the upstream and downstream taps. Write the date and the initial pressure value with an indelible marker directly on the maintenance label fixed to the casing.
  4. Checking the overall airflow at the measuring pointsCarry out a multipoint measurement grid with a Pitot tube on the main supply duct. Compare the arithmetic mean of the dynamic pressure with the commissioning data to validate full restoration of the nominal flow.

The intervention report left in the unit's technical pocket certifies the complete restoration of the airflows. This documentation protects the ventilation company against disputes relating to abnormal electricity consumption or noise nuisance caused by fans racing at maximum speed to compensate for a blocked network.

Course of action when faults persist after restart

When the twenty-minute intervention does not restore the nominal parameters, the ventilation technician must methodically isolate the source of the fault. An insufficient fresh airflow despite new filters points to upstream clogging on the outdoor air intake grille, often obstructed by leaves or insects, or to untimely closing of the frost protection damper. If the pressure drop measured with the differential manometer remains abnormal after replacing the filter media, a visual inspection of the preheating coil and the recovery wheel is required to detect surface fouling.

  1. Uncoupling the bypass actuatorIf the bypass damper refuses to close to provide heat recovery, uncouple the linkage from the actuator. Operate the shaft by hand to tell a mechanical seizure of the bearings due to dust from a blockage of electrical or logic origin.
  2. Reading the stage negative pressuresMeasure the static pressure upstream and downstream of the heat exchanger to confirm its internal tightness and to check that there is no accidental flow reversal between the extract air and the supplied fresh air.
  3. Recording the airflow deviationsDraw up a joint visit report recording the flows measured with a Pitot tube or cone, the differential pressure across the filters and the mechanical actions required outside the routine maintenance contract.

Faced with an unbalanced supply network in the rooms, the installer checks the opening of the branch dampers and the condition of the constant flow regulators, often blocked by residues from summer construction work. According to the rules of the art recognised by standard SIA 382/1, any deviation above the permissible tolerance requires an overall rebalancing rather than a one-off forcing of the fan speed.

Frequently asked questions

Why do foul odours fill the offices as soon as the unit is restarted?

During the summer break, the water in the condensate drain trap evaporates under the effect of heat. As soon as the unit is switched back on, the negative pressure created by the fan draws sewage drain gases directly in and pushes them into the air distribution. Completely filling the trap with at least two litres of lukewarm water instantly restores the water seal and blocks the foul-air backflow.

How can you spot a bypass damper actuator left stuck in summer mode?

The check is made visually on the mechanical position of the shaft or linkage of the external damper. In autumn, the outside air must pass through the plate exchanger to be preheated by the extract air. If the supply air stays cold despite a suitable extract temperature and a room setpoint that is not reached, disconnect the coupling to test whether the control forces the bypass damper closed.

Should the filters always be replaced after the summer season?

Yes, the summer months concentrate tree and grass pollen, insects and dry dust in the filter media. This load clogs the medium, increases the pressure drop by several tens of pascals and makes the nominal hygienic airflow fall. The differential pressure measurement confirms the fouling, but preventive replacement in September guarantees a compliant filtration class and avoids excess motor consumption.

What should you do if the measured overall airflow remains below the setpoint values?

First check the cleanliness of the fresh air intake grille on the facade or roof, frequently blocked by plant debris. Then check the belt tension on pulley drives, or the control voltage signal on electronically commutated motors. If the static pressures at the terminal outlets are distorted, check that no fire damper has remained in the closed standby position.