Key takeaways
- Air supply left running during a fire fans the flames and spreads toxic smoke.
- Comfort air-handling units are shut down by breaking the loop on the safety controls.
- The real test of the complete chain involves the ventilation fitter and the alarm system installer at the same time.
- The sequence test report certifies the actual travel times of the dampers and fans.
The interlock matrix requires emergency shutdown and airflow changeover
In a mechanically ventilated building, the worst scenario remains an air-handling unit that keeps injecting fresh air onto a starting fire. The oxygen supply accelerates combustion, while the duct network distributes hot, opaque gases to neighbouring rooms. The AEAI fire protection directives set a clear requirement: as soon as a detector or manual call point is triggered, the comfort ventilation of the affected compartment must be stopped immediately, or all the installations of the building according to the approved fire protection concept.
The interface between the ventilation control panel and the fire detection system is based on a fail-safe principle. The alarm signal opens a loop on loss of voltage: any wire break or power failure leads to the safe fallback state. The shutdown and smoke-extraction sequence is not just a matter of switching off a motor. It orchestrates a precise chronology of mechanical actions on the air-handling components:
- Immediate shutdown of the comfort fansRemoval of the run command on the frequency converters and opening of the power contactors of the supply and extract motors.
- Closing of the fresh-air and exhaust-air dampersRelease of the spring-return actuators on the external intakes to isolate the unit completely and cut the thermal draught.
- Targeted or general closing of the fire dampersInterruption of the power supply to the electromagnets or motors of the dampers delimiting the fire compartments concerned.
- Start-up of the smoke extraction fansStarting of the high-temperature-resistant fans and opening of the smoke exhaust dampers and the dedicated fresh-air inlet.
On the construction site, the foreman checks that the control lines of the fire dampers do not depend on a building management controller whose failure would block the transition to the safe state. The recognised rules of technology require rigid fire-resistant wiring for the mechanical smoke-control components. Art. 229 CP punishes anyone who, in directing or carrying out a construction, intentionally breaches the rules of the trade and knowingly endangers the life or physical integrity of persons. Negligence in the shutdown sequence falls directly under this liability.
The real end-to-end test and issue of the report
It is common for overall commissioning to be under pressure from the delivery deadlines of the work. Yet testing an interlock by simulating a dry contact at the back of an electrical cabinet is in no way an acceptable validation. The test of the complete chain requires triggering the alarm from the room sensor or the optical duct detector head, in order to observe the physical behaviour of each component down to the last terminal damper.
- End-to-end test
- Functional check consisting of stimulating a real alarm initiator (test smoke) and visually verifying the execution of all the mechanical commands: airflow stopped, smoke extraction fans rotating and tight closing of the shut-off devices.
| Item tested | Expected action on alarm | Physical observation on site |
|---|---|---|
| Comfort supply unit | Complete stop by safety cut-off | Impeller at standstill, no automatic restart |
| External fresh-air damper | Mechanical closing by spring | Blades closed against the stop, visibly tight |
| Zone fire dampers | Switch to safety position | Mechanical indicator on closed position, limit switch validated |
| Smoke extraction fan | Start at high speed | Direction of rotation checked, negative pressure measured in the network |
During this joint test with the fire detection technician, the ventilation fitter closely monitors sudden overpressures and negative pressures in the duct networks. A fire damper that slams shut before a powerful fan has come to a complete stop risks crushing a duct section or deforming its blades, preventing complete closing. The delay between the airflow shutdown command and the release of the compartmentation components must be set to the second.
The outcome of this process is the sequence test report. This technical document records the date, the zones stimulated, the timed response times for each unit and the final state of each damper. It is countersigned by the person responsible for the ventilation installation, the electrician and the site fire safety officer. Under art. 364 CO, the contractor is liable for the proper and faithful performance of the work; delivering an installation whose interlocks have not been proven from an airflow standpoint is a serious defect within the meaning of the contract for work.
Airflow kinematics: shutdown delays and changeover to smoke extraction
Injecting fresh air into an affected room is the critical error on an air-handling installation. Keeping the supply active amounts to fanning the fire with a continuous supply of oxidiser and putting the compartment under relative overpressure, forcing hot gases through the gaps towards stairwells or escape corridors. The AEAI fire protection directives require a strictly ordered behaviour of the air-handling components: the comfort supply must be cut before or together with the locking of the fire dampers, while mechanical smoke extraction may only start once the smoke dampers of the zone concerned are confirmed in the open position.
The ventilation fitter applies a precise kinematic sequence to the equipment under their responsibility. When the unit receives the dry contact for general or zoned release, the shutdown command acts without delay on the frequency converters and the supply contactors. The inertia of the fan impellers requires the integration of tight motorised dampers or the immediate release of the return springs of the fire dampers to block residual air sweep. In parallel, the smoke and heat exhaust installations (SHEV) or the pressurisation systems of the escape routes must follow a gradual acceleration ramp so as not to destroy the duct networks through a sudden negative pressure.
| Air-handling component (CFC 244) | Initial comfort state | Action on fire signal | Required status feedback |
|---|---|---|---|
| Comfort supply fan | Running (nominal airflow) | Power cut and braking | Differential pressure switch contact at zero |
| Compartmentation fire dampers | Open (motor energised) | Line break, closing by spring | Limit microswitches closed |
| Smoke dampers of the affected zone | Closed (tight when cold) | Opening commanded by actuator | Open limit switch contact confirmed |
| Smoke extraction fan (SHEV) | Stopped | Delayed start after the dampers have opened | Airflow control by pressure sensor |
| Stairwell pressurisation | Stopped | Immediate start at regulated overpressure | Maintaining the differential setpoint (Pa) |
Real test protocol of the chain and sequence test report
Validation of the airflow safety sequences is never done on paper or by simple software simulation. The ventilation installer carries out a test of the complete chain under real operating conditions, jointly with the electrician, the control engineer and the person responsible for the fire detection installation. Accepting the work is out of the question if a single component is forced manually or bypassed to get around a wiring fault. Every scenario defined in the fire protection concept must be run through by physically generating an alarm, zone by zone.
- Airflow preparation and bringing to nominal operationSwitch on all the air-handling units, extract fans and air curtains in normal operating mode. Check the stability of the airflows with anemometers and make sure that all the fire dampers of the network are in the armed standby position.
- Physical triggering of the fire signalHave the alarm generated at the fire detection panel for the compartment being tested. Observe the immediate sending of the emergency stop command to the ventilation cabinets and of the opening command to the smoke dampers.
- Visual check of the mechanical componentsWalk through the technical shafts and false ceilings to verify the actual closing of the zone fire dampers and the full opening of the smoke dampers. Do not rely on the controller indicator lights alone: a shaft detached from its blade shows a compliant electrical feedback while the damper remains open.
- Measurement of residual pressures and safety airflowUsing a differential manometer, measure the overpressure in the lobby or stairwell to verify compliance with the permissible range that avoids jamming the emergency doors. Record the absence of residual airflow in the supply outlets of the affected room.
- Reset procedure and return to normalAcknowledge the alarm at the main panel and carry out the motorised or manual reset of the fire dampers. Verify that the comfort ventilation does not restart erratically as long as the open position of the whole network has not been restored.
The legal and technical outcome of this process lies in the sequence test report. This contractual document, required by the cantonal fire protection authority at the acceptance of the work, records all the measurements taken, the response times of each air-handling component and any deviations observed. Under art. 364 CO, the contractor is liable for the proper and faithful performance of the work; signing a report without having observed the actual stopping of the fans and the tightness of the closures directly engages the liability of the installation company.
Handling interlock malfunctions and refusal of acceptance
On the construction site, the test of the complete chain frequently reveals critical deviations: a supply fan that keeps blowing despite the general signal, an extract damper mechanically blocked at mid-travel by a duct hanger rod, or a smoke damper whose opening command arrives with a delay incompatible with putting the affected room under negative pressure. In these situations, the ventilation fitter's reflex is often to blame the programming of the detection system or the control wiring. Yet air that keeps feeding a fire turns an incipient fire into a full blaze. The AEAI fire protection directives define an obligation of result for the safety of persons: as long as the shutdown and smoke-extraction sequence does not strictly meet the approved airflow concept, no installation can be considered operational.
- Immediate recording and refusal of sign-offIn the event of a shutdown fault or flow reversal, record the failure on the spot. Do not sign any document amounting to final commissioning without stating precisely the non-conformity observed.
- Locating the airflow or control faultDetermine with the electrician and the person responsible for the alarm whether the problem comes from the dry interface contact, a faulty actuator or mechanical friction in the duct network.
- Full repetition of the testAfter hardware or parameter correction, repeat the end-to-end test from the initial alarm trigger through to the actual measurement of pressures and component positions.
- Issue of the sequence test reportDraw up and jointly sign the sequence test report only when all the AHUs stop and the smoke extraction fans reach their nominal speed.
The sequence test report signed by all parties is the only supporting document that can be relied on at the acceptance of the work under the SIA 118 standard and at the visit of the fire protection authority. If a test fails, the reservations must block the switch to routine operation. The airflow chain must be tested end to end, under real emergency power supply conditions, to guarantee that no fresh-air ventilation will keep fanning the fire.
Frequently asked questions
What if the air-handling unit takes more than ten seconds to stop?
Excessive inertia on a supply unit is a major non-conformity with the AEAI fire protection directives. Check the wiring of the frequency converter: the fire contact must trigger the safety cut-off of the power supply or a forced rapid deceleration ramp, and not a mere software stop command via the building management network, which could needlessly delay the shutdown of the airflow.
The electrician proposes simulating the release contact with a jumper; is this acceptable?
No, this method is to be categorically rejected. Simulation by electrical bridging on the terminal block of the air-handling unit validates neither the integrity of the control line nor the real operation of the fire detection panel. The test of the complete chain requires physical activation of a detector or manual call point to prove that the information passes without loss all the way to the fan stop relays.
Who is responsible for drawing up the sequence test report?
The sequence test report is generally drawn up jointly by the fire coordination specialist, the ventilation system builder and the person responsible for the detection installation. The ventilation fitter's role is to record the final mechanical state of their equipment: complete stop of the supply fans, tight closing of the motorised fire dampers and actual opening of the smoke exhaust dampers on general release.
How to react if a smoke damper does not open during the changeover?
If a smoke damper stays closed following the alarm, the test must be interrupted immediately to avoid damaging the network through excessive negative pressure. Check for the absence of a physical obstruction in the duct, the voltage at the spring-return actuator and the continuity of the control line, then require a new complete test before any report is signed.
Texts and standards cited
- Directives de protection incendie AEAISwiss fire protection regulations on air-handling installations and mechanical smoke control
- norme SIA 118General conditions for the execution of construction work and rules for acceptance of the work
